Reporting to the supervisory delegation, Director of the Management Board of Investment and Construction of Traffic Works (Transportation Department) Luong Minh Phuc said: The Rach Dia bridge project has been approved by the City People's Committee since 2000, approved by the City People's Committee. adjusted from September 9.2017 with a length of 317,8m, including 9 spans, the width of the river crossing is 10,5m, the terrestrial part is 9,0m; the road to the bridge is about 233m long, from 14m to 27m wide. Total investment is more than 512,7 billion VND.
Currently, the Department of Transportation has transferred 100% of the compensation cost according to the approved estimate to District 7 and H. Nha Be. Up to now, there are 41/50 cases of District 7 and 28/45 cases of Nha Be side agreeing to receive compensation and hand over construction sites this June.
It is expected that the investor will start the project in June and complete the work by the end of 6. Once completed, Rach Dia bridge will help reduce the load on Rach Dia bridge 2024 on Nguyen Huu Tho street, solving 2 problem. in 1 traffic congestion points at District 4 and H. Nha Be, and at the same time shorten the travel time from Nha Be to District 7 and vice versa.
According to Mr. Luong Minh Phuc, in District 7 there are still 9/50 cases where households within the project scope have not yet agreed to receive money for handing over the premises; Nha Be encountered 17/45 cases that did not agree to receive the money for handing over the premises. Therefore, in order to speed up the completion of the project and put it into use, the investor proposed to the People's Committee of District 7 and Nha Be District to complete the compensation payment procedure for affected households and organizations. by the project and hand over the ground for the Traffic Board to start the work in June at the latest to ensure the disbursement plan.
For the Department of Planning and Investment, it is recommended to advise the City People's Committee to transfer the remaining VND 93 billion of compensation and resettlement support recorded for one project to another to increase the efficiency of capital use and disbursement rate. . At the same time, the Department of Transport prioritizes the agreement on the location of the alignment of the water supply pipeline before May 25.5 so that the Saigon Water Supply Corporation Limited will continue to carry out the procedures for the relocation of the water supply pipeline in August. handover of the bridge construction site.
At the monitoring meeting, Deputy Secretary of the Ho Chi Minh City Party Committee Nguyen Ho Hai suggested that the units cooperate to focus on removing obstacles to speed up the progress of ensuring disbursement of public investment capital. He requested the People's Committees of District 7, Nha Be District and the Traffic Department to sign a contract to coordinate the implementation of this project on schedule. At the same time, continue to mobilize people affected by the project to hand over the site to the investor.
“The coordination between the board and the departments and localities is the key step in deciding whether the project is fast or slow. Therefore, it is necessary to set up a monitoring team to grasp the situation where there is a problem and call to remove it immediately. Units check progress weekly, monthly. The goal of monitoring is to jointly coordinate and remove difficulties to accelerate the project progress, not just listen to reports and then the project is still standing still "- Mr. Nguyen Ho Hai emphasized.
Connecting Phuoc Kien commune (Nha Be) and Tan Phong ward (District 7), Rach Dia 2 bridge "carrys" a large number of vehicles pouring from the southern urban area of the city towards the center. The situation of traffic jams, many people climb the pedestrian area on this bridge often happens. Rach Dia Bridge 2 and Kenh Te Bridge are known as the two "bottlenecks" that are "strangling" the traffic in the South of Ho Chi Minh City.