Mr. Vo Van Quang, Deputy Project Manager, Bien Dong Construction and Consulting Joint Stock Company (construction contractor) said that after completion, Hong Ngu Bridge will have a horizontal clearance of 5.5m greater and be 2m higher than the old bridge.
Contractor urgently raises clearance of Hong Ngu bridge in Hong Ngu city ( Dong Thap ).
The bridge was started at the end of May 2024. After four months of construction, the contractor has completed 2/8 piers, 1/2 bridge abutments and 21/58 bored piles.
Immediately upon implementation, the contractor arranged two construction teams. At the same time, workers were organized to work two shifts throughout the project when weather conditions were favorable.
"According to the amount of work done, the project's construction progress has reached 20%. In the coming time, the contractor will continue to speed up construction and complete the assigned work according to regulations," said Mr. Quang.
According to Mr. Quang, although the work is progressing smoothly, this week the contractor will begin constructing the first piles under the river.
The contractor has prepared sufficient manpower and equipment to construct the first pile under the river.
To do this, the contractor has gathered all the necessary machinery and equipment in the past week. At the same time, the company has also organized workers to perform related tasks before piling.
"Hong Ngu Bridge has 16 piles under the river. According to calculations, the contractor will complete it within two months.
It is expected that in early October, after the items on this side of the bridge are basically completed, the contractor will continue to organize workers to construct the work on the other side of the bridge, in An Thanh ward, Hong Ngu city," Mr. Quang informed.
Mr. Tran Van Tuan, the consulting and supervising unit of Hong Ngu bridge, assessed that the contractor basically ensured the progress according to the proposed construction plan. However, the implementation is still difficult due to the land clearance problem at the bridge head in An Thanh ward. He also said that the locality is making efforts to have a clean land for the construction unit.
Hong Ngu Bridge has a total land area to be recovered of more than 1.6 hectares and 95 households are compensated.
Source: https://www.baogiaothong.vn/cau-hong-ngu-o-dong-thap-hien-thi-cong-den-dau-192240916180609146.htm