How is the construction of Hong Ngu Bridge in Dong Thap?

Báo Giao thôngBáo Giao thông17/09/2024


Mr. Vo Van Quang, Deputy Project Manager, Bien Dong Construction and Consulting Joint Stock Company (construction contractor) said that after completion, Hong Ngu Bridge will have a horizontal clearance of 5.5m greater and be 2m higher than the old bridge.

Cầu Hồng Ngự ở Đồng Tháp hiện thi công đến đâu?- Ảnh 1.

Contractor urgently raises clearance of Hong Ngu bridge in Hong Ngu city ( Dong Thap ).

The bridge was started at the end of May 2024. After four months of construction, the contractor has completed 2/8 piers, 1/2 bridge abutments and 21/58 bored piles.

Immediately upon implementation, the contractor arranged two construction teams. At the same time, workers were organized to work two shifts throughout the project when weather conditions were favorable.

"According to the amount of work done, the project's construction progress has reached 20%. In the coming time, the contractor will continue to speed up construction and complete the assigned work according to regulations," said Mr. Quang.

According to Mr. Quang, although the work is progressing smoothly, this week the contractor will begin constructing the first piles under the river.

Cầu Hồng Ngự ở Đồng Tháp hiện thi công đến đâu?- Ảnh 2.

The contractor has prepared sufficient manpower and equipment to construct the first pile under the river.

To do this, the contractor has gathered all the necessary machinery and equipment in the past week. At the same time, the company has also organized workers to perform related tasks before piling.

"Hong Ngu Bridge has 16 piles under the river. According to calculations, the contractor will complete it within two months.

It is expected that in early October, after the items on this side of the bridge are basically completed, the contractor will continue to organize workers to construct the work on the other side of the bridge, in An Thanh ward, Hong Ngu city," Mr. Quang informed.

Mr. Tran Van Tuan, the consulting and supervising unit of Hong Ngu bridge, assessed that the contractor basically ensured the progress according to the proposed construction plan. However, the implementation is still difficult due to the land clearance problem at the bridge head in An Thanh ward. He also said that the locality is making efforts to have a clean land for the construction unit.

Hong Ngu Bridge has a total land area to be recovered of more than 1.6 hectares and 95 households are compensated.



Source: https://www.baogiaothong.vn/cau-hong-ngu-o-dong-thap-hien-thi-cong-den-dau-192240916180609146.htm

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product