NDO - These days, the consortium of contractors is carrying out the installation of the steel roof structure for the passenger terminal at Long Thanh International Airport (Long Thanh Airport) Phase 1. This is one of the important tasks of the "heart" of the Long Thanh airport project. This is also the project with the largest total investment capital in the history of our country to date. Reporters from Nhan Dan Newspaper recorded images of the bustling construction at the Long Thanh airport construction site today, August 29th.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 2)

The total weight of steel structures for erecting the roof frame of the Long Thanh airport passenger terminal in phase 1 is approximately 32,000 tons.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 3)

Workers and engineers are installing steel structures to construct the roof of the Long Thanh airport passenger terminal.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 4)

After being lifted onto the roof, the workers proceeded with the installation of the steel structure.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 5)

The steel structure for the roof of the two side wings of the terminal building is being installed. It is expected that the steel structure for the main passenger terminal roof will be installed in September.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 6)

The passenger terminal building is considered the "heart" of Long Thanh Airport's first phase. Along with installing the steel structure, the construction units are also working on the concrete floor and main pillars of the terminal.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 7)

Meanwhile, for package 4.6, the runway and aircraft parking area are under construction, with the finishing concrete layer being applied.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 9)

As for the Control Tower, which is part of Component 2 and is being invested in by the Vietnam Air Traffic Management Corporation, construction is also progressing rapidly.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal (image 10)

According to ACV, phase 1 of Long Thanh Airport is expected to be completed and trial operations finished before August 31, 2026. On September 2, 2026, Long Thanh Airport will welcome its first commercial flight.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal, photo 12

The Long Thanh Airport construction project, located in Long Thanh district, Dong Nai province, has an estimated total investment of over 16 billion USD, divided into 3 phases. Phase 1 alone is worth over 5.4 billion USD.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal, photo 13

Long Thanh Airport Phase 1 is a nationally important project with significant implications for the socio-economic development of our country. It includes one runway and one passenger terminal, along with supporting facilities, with a capacity of 25 million passengers per year and 1.2 million tons of cargo per year.

[Image] Erecting the steel frame for the roof of Long Thanh Airport terminal, photo 14

Upon completion of all phases, Long Thanh Airport is expected to reach a capacity of up to 100 million passengers per year and become the largest airport in Vietnam in the future, aiming to become one of the international air transit hubs in the region.



Source: https://nhandan.vn/anh-lap-dung-khung-thep-mai-nha-ga-san-bay-long-thanh-post827465.html

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Di sản

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Traditional boat racing in Da Nang City

Traditional boat racing in Da Nang City

Happy

Happy

Belief in the worship of King Hung

Belief in the worship of King Hung