Comrade Tran Minh Trung inspected the progress of the bidding package at the section in Long Binh commune. |
According to the Project Management Board, the package includes the following items: Road section, Phuoc Trung bridge, Long Binh culvert.
The road section starts at the existing provincial road 877 in Long Binh commune; the end point is at Km4+680, in Tan Hoa commune. The length of the route is about 4.68 km (including Long Binh culvert and Phuoc Trung bridge). The axle load is designed to be 10 tons.
Comrade Tran Minh Trung inspected the progress of the package at the intersection with provincial road 872B. |
The project is constructed by Phuoc Hung Construction Service Trading Company Limited and Minh Thai Construction Service Trading Company Limited. The contract package started on June 26, 2025 and is expected to be completed on June 21, 2026.
Checking the progress of the bidding package at the Phuoc Trung bridge construction area. |
Currently, contractors are focusing on gathering materials and equipment to the construction site; clearing and cleaning the construction site.
Contractors are focusing on speeding up the progress of the package. |
During the inspection, comrade Tran Minh Trung requested contractors to focus on mobilizing human resources, equipment, and materials to speed up the progress of the package, ensuring completion on schedule and quality.
Mr. THANH