The problem has been fixed, Unit 1

Việt NamViệt Nam12/08/2023

After troubleshooting, at 8:56 a.m. on August 12, Unit 1 of Vung Ang 1 Thermal Power Plant ( Ha Tinh Petroleum Power Company) officially reconnected to the national grid after nearly 2 years of suspension.

In September 2021, Unit 1 of Vung Ang 1 Thermal Power Plant (Ky Loi Commune, Ky Anh Town) encountered a technical problem and had to temporarily stop operations.

After the problem was fixed, Unit 1 of Vung Ang 1 Thermal Power Plant reconnected to the national grid.

After many efforts, the technical problem at Unit 1 of Vung Ang 1 Thermal Power Plant has been successfully resolved.

With the timely and effective direction of Vietnam Oil and Gas Power Corporation, Ha Tinh Oil and Gas Power Company has deployed periodic repair work combined with troubleshooting and repairing Unit 1 to ensure proper technical standards.

After the problem was fixed, Unit 1 of Vung Ang 1 Thermal Power Plant reconnected to the national grid.

The leaders of the Vietnam Oil and Gas Power Corporation promptly directed and encouraged the staff and workers of the Ha Tinh Oil and Gas Power Company to successfully reconnect generator unit 1 to the grid.

On August 12, 2023, leaders of Vietnam Oil and Gas Power Corporation and contractor leaders came to direct and encourage officers and workers of Ha Tinh Oil and Gas Power Company and contractors at the important moment - bringing Unit 1 of Vung Ang 1 Thermal Power Plant back to the grid.

After the problem was fixed, Unit 1 of Vung Ang 1 Thermal Power Plant reconnected to the national grid.

At 8:56 a.m. on August 12, 2023, Unit 1 of Vung Ang 1 Thermal Power Plant officially reconnected to the national grid.

Mr. Tran Van Tinh - Deputy Director of Ha Tinh Petroleum Power Company excitedly said: "After many efforts, at 8:56 a.m. on August 12, 2023, Unit 1 of Vung Ang 1 Thermal Power Plant was officially connected to the national grid. Putting Unit 1 back into operation is of great significance in ensuring national energy security, serving the development of the country's economy ".

After the problem was fixed, Unit 1 of Vung Ang 1 Thermal Power Plant reconnected to the national grid.

Putting Unit 1 back into operation is of great significance in ensuring national energy security.

In the coming time, Ha Tinh Oil and Gas Power Company will focus on operating the factory safely and effectively, completing the assigned production and business plan.

At the same time, choose long-term strategies and plans to ensure adequate coal supply to meet the plant's operational needs; proactively carry out maintenance and repair of equipment systems, improve the availability of generators, etc.

Thu Phuong


Source

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Notre Dame Cathedral in Ho Chi Minh City is brightly lit to welcome Christmas 2025
Hanoi girls "dress up" beautifully for Christmas season
Brightened after the storm and flood, the Tet chrysanthemum village in Gia Lai hopes there will be no power outages to save the plants.
The capital of yellow apricot in the Central region suffered heavy losses after double natural disasters

Same author

Heritage

Figure

Enterprise

Dalat coffee shop sees 300% increase in customers because owner plays 'martial arts movie' role

News

Political System

Destination

Product

Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC
Footer Banner Agribank
Footer Banner LPBank
Footer Banner MBBank
Footer Banner VNVC