Construction site for the Da Lat ring road is in disarray.

The Cam Ly - Phuoc Thanh road construction project, intended to serve the transportation needs of residents and tourists and alleviate traffic congestion in the Da Lat area of ​​Lam Dong province, remains unfinished and behind schedule despite repeated urging from the Lam Dong Provincial People's Committee.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng14/05/2026

Video : Current status of the Cam Ly – Phuoc Thanh road construction project. Produced by: DOAN KIEN

The Cam Ly - Phuoc Thanh road project is 8.9km long, connecting Cam Ly ward in Da Lat and Lang Biang ward in Da Lat, linking the western to the northern part of Da Lat. In 2022, the Lam Dong Provincial People's Committee approved the project with a total investment of 400 billion VND.

The investment objective for this road project is to create a ring road axis in accordance with the Da Lat urban master plan until 2030, with a vision to 2050.

70a475296d35ec6bb524.jpg
A section of the newly opened road as part of the Cam Ly – Phuoc Thanh road construction project. Photo: DOAN KIEN

According to the initial plan, the project was to be implemented during the period 2021-2024, then adjusted to the end of 2025. However, due to land clearance issues, the project has been repeatedly delayed compared to the plan.

To date, only the section from Cam Ly intersection to Mang Ling, intersecting with Ankroet road, approximately 5.2km long, has been basically completed. The remaining sections are still unfinished. Specifically, the new section from Km4+556 of DT.722 road to the intersection with 19-5 road in Lang Biang ward, Da Lat, still faces numerous challenges in land clearance and site leveling.

351bb2ffaae32bbd72f2.jpg
The newly opened road passes through the production area of ​​the people in Lang Biang ward, Da Lat, with Lang Biang mountain in the distance. Photo: DOAN KIEN

Due to the project's delays, Vice Chairman of the Lam Dong Provincial People's Committee Vo Ngoc Hiep inspected the site and requested that the relevant units urgently concentrate manpower and equipment to quickly complete the site preparation for construction, aiming for completion before June 30, 2026.

A06A3957.JPG
In some sections, a few workers were scattered around, constructing the road's drainage system. Photo: DOAN KIEN

According to the Lam Dong Provincial People's Committee, upon completion, the project will serve the transportation and goods delivery needs of residents and tourists, contributing to reducing traffic congestion in the Da Lat area.

The project also seamlessly connects with the 7.4km-long Da Lat ring road, with a total investment of 870 billion VND. Construction on this route began in July 2021 and is now largely complete, allowing vehicles to travel from the southern part of Da Lat, between Prenn Pass, to the west, towards Cam Ly Waterfall.

>> Some images recorded by SGGP Newspaper at the scene:

IMG_8736.JPG
IMG_8739.JPG
Currently, the project is still facing obstacles due to approximately 80 meters of land that have not yet been cleared. Photo: DOAN KIEN
IMG_8718.JPG
In areas with cleared land, workers proceed with clearing and leveling the terrain. Photo: DOAN KIEN
IMG_8730.JPG
A section of concrete retaining wall is under construction. This location was previously a hill that was leveled to make way for a new route in the project. Photo: DOAN KIEN
86c4fe1ae60667583e17.jpg
The completed road will connect the western and northern areas of Da Lat, Lam Dong province. Photo: DOAN KIEN
A06A3833.JPG
The section from the Mang Ling intersection to Km4+556 on provincial road DT.722 (coinciding with provincial road DT.722) has not yet been repaved with asphalt. Photo: DOAN KIEN
IMG_8705.JPG
Currently, the project has paved over 80% of the entire route with asphalt. Photo: DOAN KIEN
A06A3819.JPG
Some sections of asphalt that were laid a few months ago are being repaved. Photo: DOAN KIEN
A06A3876.JPG
In the area where the new route passes through, people are building houses and greenhouses to support production. Photo: DOAN KIEN
IMG_8744.JPG
The project to build a new bridge has now basically completed the rough construction phase. Photo: DOAN KIEN
IMG_8751.JPG
The project's endpoint intersects with May 19th Street (Lang Biang Ward – Da Lat). Photo: DOAN KIEN

Source: https://www.sggp.org.vn/ngon-ngang-cong-truong-duong-vanh-dai-da-lat-post852532.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Visiting the martyrs' cemetery.

Visiting the martyrs' cemetery.

Fish

Fish

The Grilled Restaurant of Fond Memories

The Grilled Restaurant of Fond Memories