Lam Dong province sets a deadline for resolving obstacles for 128 investment projects.

The departments and agencies of Lam Dong province unanimously agreed on the need to focus intensely on resolving each group of obstacles definitively according to specific timelines for each investment project in the area.

Báo Lâm ĐồngBáo Lâm Đồng18/05/2026

dscf8765(1).jpg
Scene from the working session

On the afternoon of May 18th, Provincial Party Committee member and Vice Chairman of the Lam Dong Provincial People's Committee, Vo Ngoc Hiep, chaired a meeting with Task Force No. 3 to review progress, clearly define responsibilities, and propose solutions to overcome difficulties and obstacles for investment projects in the province.

According to the report at the meeting, Task Force No. 3 was assigned by the Provincial People's Committee to handle difficulties and obstacles for 128 projects. To expedite the processing, the task force assigned 8 departments and agencies and 7 communes and wards to research and propose specific solutions according to the functions and authority of each unit.

Among the assigned agencies, the Department of Finance is responsible for 61 projects. To date, the department has resolved difficulties for 6 projects; completed reports and submitted proposals to the Provincial People's Committee for consideration of 2 projects; and proposed removing 2 projects from the monitoring list.

This is a large-scale project group with many aspects related to financial obligations, procedures, and issues that require thorough review before being submitted to competent authorities for consideration and decision.

dscf8762(1).jpg
Director of the Finance Department, Ton Thien San, presented a report on the status of the projects at the meeting.

Regarding the tax sector, currently 12 out of 103 projects have outstanding financial obligations totaling over 1,230 billion VND. This is an issue that relevant departments and agencies consider crucial, as financial obligations are one of the important conditions for projects to complete procedures, implement investments, or adjust related aspects.

dscf8780.jpg
Representatives from the Lam Dong Provincial Tax Department expressed their opinions at the meeting.

At the meeting, the departments and agencies unanimously agreed on the need to focus intensely on resolving each group of obstacles definitively according to specific timelines. Initially, the units will strive to complete the removal of obstacles related to tax and finance projects before June 10th.

At the same time, we request that the Provincial People's Committee direct a 30% reduction in the time required for administrative procedures, in order to resolve outstanding issues related to project schedule adjustments by June 20th.

dscf8774(1).jpg
Representatives from various departments, agencies, and localities attended the working session.

In addition, the task force will continue to review and classify projects that are still facing difficulties in land clearance; and projects currently under inspection by the Provincial Inspectorate, in order to determine appropriate solutions that comply with regulations but do not cause delays or slow down the overall progress.

For the 6 out of 12 projects that have been updated on the 751 database system, the units are required to focus on reviewing the files and carefully studying Government Decree No. 147 on specific mechanisms and policies to resolve difficulties and obstacles for stalled and long-standing projects.

dscf8788(1).jpg
Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep gave instructions at the working session.

Directing the meeting, Vice Chairman of the Provincial People's Committee Vo Ngoc Hiep requested that departments, agencies, and localities closely monitor each project and each group of obstacles; clarify responsibilities, authority, and deadlines for resolution.

Removing obstacles to the project must be substantive, yielding concrete results, contributing to unlocking investment resources, and promoting the socio -economic development of the province.

Source: https://baolamdong.vn/lam-dong-dat-moc-thoi-gian-thao-go-vuong-mac-cho-128-du-an-dau-tu-442622.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
He takes care of her.

He takes care of her.

Sinh viên Việt Nam năng động - tự tin

Sinh viên Việt Nam năng động - tự tin

Nét xưa

Nét xưa