The unit has completed the construction of global bored piles, completed all 2 bridge piers, completed the construction of the M2 abutment base and wall, completed the loading of the roadbed at both ends of the bridge...
Currently, we are constructing granular material behind pier M2, monitoring settlement of pier M1, and preparing to deploy construction on both sides of the wing road...
Phi Xa Bridge connects Le Hong and Tu Cuong communes (Thanh Mien) across Cuu An River, on the East-West axis at km 6 + 833, the bridge length is 154 m with 3 super T girder spans. The bridge has 2 abutments and 2 pillars made of reinforced concrete placed on bored piles, the bridge cross-section is 12m. The total construction value is about 48 billion VND. The project is expected to be completed on April 30, 2024.
PVSource