The contractor has completed the global bored pile construction, finished both bridge piers, completed the abutment base and retaining walls of pier M2, and completed the embankment loading at both ends of the bridge…
Currently, construction is underway on filling the M2 embankment with granular material, monitoring settlement is being carried out at the M1 embankment, and preparations are being made to deploy embankment on both sides of the wing road...
The Phi Xa Bridge connects Le Hong and Tu Cuong communes (Thanh Mien district) across the Cuu An River, on the East-West axis at km 6 + 833. The bridge is 154 meters long with 3 Super T girder spans. It has 2 abutments and 2 piers made of reinforced concrete placed on a system of bored piles, with a cross-section of 12 meters. The total construction cost is approximately 48 billion VND. The project is expected to be completed on April 30, 2024.