Da Nang extends deadline for the over 151 billion VND project for the "final time".

The Tam Giang Bridge project, with a capital of over 151 billion VND, remains unfinished after many years. Vice Chairman of the Da Nang City People's Committee, Tran Nam Hung, instructed relevant units to resolve the obstacles and emphasized that this is the final extension of the deadline.

Báo Đầu tưBáo Đầu tư29/12/2024

The Tam Giang Bridge project has a total investment of over 151 billion VND, with a bridge length of 210.5 m and approach roads at both ends totaling 469.5 m. The project aims to improve infrastructure, meet socio -economic development requirements, and ensure national security and defense.

Construction on the project began in 2017 and was expected to be completed in July 2018. However, after several adjustments to the project timeline, it remains unfinished to this day.

According to the Quang Nam Investment and Construction Project Management Board, the project currently requires approximately 10,000 m3 of fill soil. However, the local soil resources are scarce and cannot meet the project's needs, significantly impacting the construction of the roadbed section leading to Tam Giang commune (formerly).

The Tam Giang bridge project has been underway for many years but is still not finished.

After the dissolution of the district-level authority, the project was transferred to the Quang Nam Provincial Investment and Construction Project Management Board. However, to date, the competent authority has not yet allocated the necessary funds, causing difficulties in the implementation process.

Furthermore, the project has been delayed for many years due to compensation and land clearance issues. Currently, the construction contractor is facing financial difficulties, which is hindering the implementation of the project.

You may also like
A surprising "wave" of exploring destinations in Central Vietnam.
A surprising "wave" of exploring destinations in Central Vietnam.VHO - According to data from Traveloka, along with Phu Quoc, Da Nang is currently the most searched-for accommodation destination on the platform in Vietnam.
The Ministry of Construction will submit its rental housing policy in October.
The Ministry of Construction will submit its rental housing policy in October.In the context of continuously rising housing prices, far exceeding the affordability of the majority of the population, developing rental housing is being identified as one of the strategic solutions.
The 870 billion VND Da Lat ring road project repeatedly misses deadlines.
The 870 billion VND Da Lat ring road project repeatedly misses deadlines.TPO - After years of delays, the Da Lat ring road project in Lam Dong province continues to miss its deadline because seven households have yet to hand over their land, causing construction to be delayed.

In light of these obstacles, the investor requests the Da Nang City People's Committee to resolve the difficulties regarding the need for fill soil for the project, and to promptly allocate funds to complete the remaining work.

The City Land Development Center is directed to expedite the compensation and land clearance process for the Tam Giang Bridgehead Landscape Improvement Project on the Nui Thanh town side, and to hand over the land for the construction of the drainage ditch.

Currently, the bridge is in a state of disrepair, with structural damage affecting traffic safety on the route. Therefore, the Project Management Board proposes that the City People's Committee consider and approve the immediate plan to complete the asphalt paving of the bridge surface and approximately 240m of approach roads on both sides, connecting them to the existing road, and supplementing traffic organization to hand over for operation to alleviate traffic congestion on the old Tam Giang Bridge. The remaining items will continue to be implemented and completed in the fourth quarter of 2025.

The project's implementation period expires on August 26, 2025. Therefore, the Management Board requests the City People's Committee to consider and agree to extend the contract execution period for the construction package of the project until the end of November 2025.

The Vice Chairman of the Da Nang City People's Committee (wearing a blue hat) directs the removal of obstacles to the Tam Giang Bridge Project.

During a site inspection, Mr. Tran Nam Hung, Vice Chairman of the Da Nang City People's Committee, requested that the relevant units urgently complete the project. Specifically, the second layer of asphalt paving must be completed by October 30th, ensuring smooth traffic flow on the new bridge to alleviate congestion on the old one. The entire project must be completed and put into operation by 2025.

You may also like
Young people are ready to celebrate the big day.
Young people are ready to celebrate the big day.On June 23rd, delegations from all over the country arrived in Hanoi to attend the 13th National Congress of the Vietnam Youth Union, for the term 2026-2031. The atmosphere of anticipation for this great event for young people also spread throughout the capital.
Most transportation projects in Dong Nai are facing land acquisition issues.
Most transportation projects in Dong Nai are facing land acquisition issues.On April 8th, the Dong Nai Provincial Investment and Construction Project Management Board announced that there are currently 45 transportation projects in the province, of which 30 have been allocated funding, while the rest have not yet started construction. In most of the ongoing projects, the issue is that the land has not been fully handed over, leading to project delays.
USD/VND exchange rate today, June 24th: Black market rate surges by nearly 60 dong.
USD/VND exchange rate today, June 24th: Black market rate surges by nearly 60 dong.Today, June 24th, the USD/VND exchange rate in the black market is trading at 26,549 - 26,649 VND/USD, an increase of 58 VND in both buying and selling rates compared to yesterday morning.

Regarding the project timeline, Mr. Tran Nam Hung approved the adjustment of the project schedule and emphasized that this would be the final timeframe for this project.

Source: https://baodautu.vn/da-nang-gia-han-tien-do-lan-cuoi-cho-du-an-hon-151-ty-dong-d366218.html

Trending by Category

Most Read

Google Trends

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
The Gentle Charm of Hue

The Gentle Charm of Hue

innocent childhood

innocent childhood

Trang An Festival

Trang An Festival