Da Nang speeds up completion of key projects

Lien Chieu Port project - the shared infrastructure part has completed more than 84% of the total investment, while the coastal road connecting Lien Chieu Port has also completed nearly 60%.

Báo Đầu tưBáo Đầu tư29/12/2024

Da Nang City is speeding up the completion of a series of key, dynamic projects that have a great impact on the city's socio -economic development.

Of which, by the end of August 2025, the Lien Chieu Port Construction Investment Project - shared infrastructure part has reached 2,894 billion VND, equivalent to 84.5% of the total investment.

The Lien Chieu Port Construction Investment Project - shared infrastructure part has a total investment of VND 3,426.3 billion, starting in December 2022 and expected to be completed by the end of 2025.

Meanwhile, the coastal road project connecting Lien Chieu Port is also being focused on by Da Nang city, because this is an important project to synchronize and connect with Lien Chieu port.

The coastal road connecting Lien Chieu port has a total investment of 1,203 billion VND, as of the end of August 2025, the implemented value reached 694.2 billion VND, equal to 57.7% of the total project investment. Of which, the implemented value from the beginning of 2025 to the end of August is estimated at 262 billion VND, equal to 74.1% of the plan assigned for the year.

Lien Chieu seaport project is expected to be completed by the end of 2025.

To connect the coastal route, Da Nang city also focuses on the project to complete coastal road 129 (Vo Chi Cong street). It is estimated that from the start of construction to the end of August 2025, the project's implementation value will reach 255 billion VND, equal to 33.1% of the planned capital allocated for the year and 12.4% of the total investment.

The total investment for the 129 coastal road completion project is over VND2,056 billion. Of which, the central budget is VND1,558 billion; the local budget is over VND498.7 billion.

The project aims to complete coastal traffic infrastructure, inter-regional connectivity between Da Nang - Hoi An - Chu Lai - Quang Ngai; promote tourism , attract investment, and ensure national defense and security in coastal areas.

Meanwhile, the Hoi An Coastal Erosion Prevention and Sustainable Protection Project, allocated VND396.7 billion from foreign direct investment (ODA) in 2025, by the end of August 2025 had reached VND188.6 billion, equal to 47.5% of the capital plan assigned for the year and 19.2% of the total investment.

The Hoi An Coastal Erosion Prevention and Sustainable Protection Project has a total investment of VND982,239 billion, equivalent to 42 million Euros.

Of which, the loan capital from the French Development Agency (AFD) is 807.745 billion; non-refundable aid from the WARM fund authorized by the European Union (EU) is 46.585 billion VND; counterpart capital from the local budget is 127.907 billion VND.

Source: https://baodautu.vn/da-nang-tang-toc-hoan-thanh-cac-cong-trinh-trong-diem-d382503.html


Comment (0)

No data
No data

Same tag

Same category

There is a hill of purple Sim flowers in the sky of Son La
Lantern - A Mid-Autumn Festival gift in memory
Tò he – from a childhood gift to a million-dollar work of art
Efforts to preserve the traditional Mid-Autumn toy making craft in Ong Hao village

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product