TPO - The Hanoi Urban Railway Project Management Board (MRB) has proposed to the Hanoi People's Committee to allow commercial operation of the elevated section of the Nhon - Hanoi Station urban railway (Metro) project from August 9th.
MRB stated that the proposal was made after the elevated section of the project from Nhon to Cau Giay was evaluated (the final stage) by the State Inspection Council and approved for commercial operation.
In order for the elevated section to be put into passenger service, MRB proposed that the City People's Committee organize its completion and commercial operation by August 9th.
In addition, MRB recommends that the City People's Committee consider assigning tasks to relevant agencies and units. Specifically, the Department of Transport should direct its Inspection force to coordinate with traffic police and other relevant units to agree on a plan for organizing traffic flow to ensure smooth traffic.
The People's Committees of Bac Tu Liem, Nam Tu Liem, Cau Giay, Ba Dinh, and Dong Da districts organized environmental sanitation, preventing people from dumping garbage and waste materials on the sidewalks along both sides of the road, ensuring traffic safety and public order; and implemented decorations to commemorate the 70th anniversary of the Liberation of Hanoi in the train station area...
The Nhon - Hanoi Station metro project is 12.5km long, including an 8.5km elevated section (Nhon - Cau Giay) and a 4km underground section (Cau Giay - Hanoi Station). When the elevated section is operational, each train will carry approximately 1,000 passengers, and each train will carry more than 8,000 passengers per hour in each direction.
Source: https://tienphong.vn/de-xuat-van-hanh-metro-nhon-ga-ha-noi-tu-ngay-98-post1660339.tpo