Removing obstacles related to construction materials for the North-South Expressway Project.

Báo Thái NguyênBáo Thái Nguyên05/07/2023


Prime Minister Pham Minh Chinh recently signed and issued Official Dispatch No. 573/CD-TTg on resolving difficulties and obstacles related to the exploitation and supply of common construction materials for the North-South Expressway Project (Eastern section) giai đoạn 2021-2025.

The contractor is working on the eastern section of the North-South Expressway. (Photo by T.L)
The contractor is constructing the eastern section of the North-South Expressway. (Photo courtesy)

The official dispatch states: The North-South Expressway Project (Eastern section) for the period 2021-2025 (hereinafter referred to as the Project) commenced on January 1, 2023. However, to date, some contract packages are still facing difficulties regarding the supply of common construction materials. The People's Committees of the provinces have only completed the registration procedures for 14 mines out of a total of 51 mines that have been submitted by the investor and contractors... The main reason is that some agencies and localities have not made sufficient efforts to actively implement the Prime Minister 's directives in the past.

To ensure the progress and quality of the project, the Prime Minister requests that ministers of ministries and chairmen of People's Committees of provinces and cities through which the project passes strictly implement the resolutions, official dispatches, and conclusions of the Government and the Prime Minister to take decisive and timely measures to overcome difficulties and obstacles in the exploitation and supply of construction materials for expressway construction projects.

The Chairpersons of the People's Committees of provinces and cities where the Project passes through and where common construction material mines are included in the Project dossier shall direct the relevant provincial agencies and local authorities to urgently resolve the registration procedures for mining operations submitted by contractors in accordance with the guidelines of the Ministry of Natural Resources and Environment, completing them before June 30, 2023; coordinate with the project investors to review and increase the capacity of licensed and currently operating stone, sand, and soil mines in the area to meet the needs and construction progress...

The Minister of Transport has established a working group comprising leaders from the Ministries of Natural Resources and Environment, Construction, Agriculture and Rural Development, Public Security, and other relevant agencies to urgently inspect and work with the provinces and cities in the Project area to promptly address related obstacles; and to report to the Prime Minister before July 15, 2023.



Source link

Comment (0)

Please leave a comment to share your feelings!

Same category

The Christmas atmosphere is vibrant on the streets of Hanoi.
Enjoy the exciting night tours of Ho Chi Minh City.
A close-up view of the workshop making the LED star for Notre Dame Cathedral.
The 8-meter-tall Christmas star illuminating Notre Dame Cathedral in Ho Chi Minh City is particularly striking.

Same author

Heritage

Figure

Enterprise

The moment Nguyen Thi Oanh sprinted to the finish line, unrivaled in 5 SEA Games.

News

Political System

Destination

Product