Vice Chairman of the Provincial People's Committee Le Duc Tien inspected the site clearance work of the coastal road connecting the East-West economic corridor, Quang Tri province, phase 1 through Gio Linh district - Photo: LA
The Coastal Road Project connecting the East-West Economic Corridor, Quang Tri Province, Phase 1 has a route length of about 48 km passing through Vinh Linh, Gio Linh, Trieu Phong districts and Dong Ha City. The project has a total investment of VND 2,060 billion, with implementation period from 2021 to 2026.
Up to now, localities have handed over 25 km/48 km of land. Of which, Vinh Linh district has handed over 6.3 km/23.06 km; Gio Linh district has handed over 9.26 km/12.4 km. The remaining sections are expected to be handed over in 2025. The value of implementation to date has reached 549 billion VND.
Vice Chairman of the Provincial People's Committee Le Duc Tien inspected the site clearance work of the coastal road connecting the East-West economic corridor, Quang Tri province, phase 1 through Vinh Linh district - Photo: LA
Regarding resettlement, Vinh Linh district has 48 resettled households, of which Cua Tung town has 17 households, Kim Thach commune has 10 households, Vinh Thai commune has 21 households. It is expected that Cua Tung town will have 1 resettlement area; Vinh Thai commune will have 2 resettlement areas; Kim Thach commune will provide land for on-site resettlement. Gio Linh district has 22 resettled households, of which Cua Viet town has 20 households and Trung Giang commune has 2 households. Currently, the People's Committees of the 2 districts are implementing this.
Construction of coastal road connecting East-West economic corridor, Quang Tri province, phase 1 through Gio Linh district - Photo: LA
Regarding construction work, the 23.06 km section through Vinh Linh district has basically completed 2/3 of the bridge; the road section has constructed the roadbed for 6.3 km/23.06 km. The value of implementation to date is 17 billion VND/309 billion VND, reaching 5.4%.
The 12.4 km section through Gio Linh district is currently under construction of 2.9 km/12.4 km of roadbed earth; 5/37 horizontal drainage culverts are under construction. The value of implementation to date is 16.5 billion VND/245 billion VND, reaching 6.7%.
Construction of horizontal drainage at the coastal road project connecting the East-West economic corridor, Quang Tri province, phase 1 through Gio Linh district - Photo: LA
The current difficulties and obstacles are due to changes in policies, regulations and laws of the State, and adjustments to the route to suit the current situation, so the costs of some items including resettlement, site clearance, construction costs... have arisen, expected to increase by about 681 billion VND compared to the total approved investment. These additional costs have not been approved and arranged, which will greatly affect the progress of site clearance, construction of resettlement areas and the progress of disbursement of central capital allocated for construction and installation.
Localities have not completed the relocation of infrastructure and technical works; have not completed the work of determining the origin of land use, building resettlement areas and clearing forests owned by the people and managed by the State. Vinh Linh district has not approved the land use plan for 2025, so according to regulations, it is not allowed to approve the compensation and land recovery plan.
For the coastal road project, the section through Cua Tung and Cua Viet bridges has a total investment of 600 billion VND, and is scheduled to be completed in 2025. Of which, the section through Cua Tung bridge is 3.16 km long, starting at the intersection with DT.574 road in Vinh Linh district, and ending at the intersection with DT.576 Dong road in Gio Linh district.
Currently, the GPMB stake placement work has been completed, and the cadastral survey work is being completed. It is expected that the land acquisition notice will be submitted before April 20; the land inventory will be organized after the land acquisition notice is issued in April 2025; the public price will be applied in May 2025; the compensation and support plan will be approved and the site will be handed over in June 2025.
After the on-site inspection, Vice Chairman of the Provincial People's Committee Le Duc Tien requested the contractor to take advantage of favorable weather to urgently mobilize additional machinery and personnel to work overtime and increase shifts to speed up the construction progress. Vinh Linh and Gio Linh districts should strengthen propaganda and mobilize people to agree on compensation and support for land acquisition and clearance; speed up the progress of determining the origin of land use and land use rights to promptly hand over the site to the contractor. Assign relevant departments and branches to closely coordinate with the Provincial Investment and Construction Project Management Board in appraising and adjusting the investment policy to promptly submit to the Provincial People's Council for approval to speed up the land acquisition and clearance work and complete the project according to the approved schedule.
Le An