Reasons for the multi-billion VND road project in Ba Ria.

Việt NamViệt Nam05/08/2024


TPO – The project for the road north of Ba Ria Hospital is invested by the People's Committee of Ba Ria City, Ba Ria – Vung Tau province, with a total investment of 110 billion VND. The project started in December 2021 but is still unfinished due to land acquisition issues.

On August 4th, Mr. Tran Thanh Dung, Chairman of the People's Committee of Ba Ria City, Ba Ria - Vung Tau province, announced that the local authorities will enforce land reclamation to expedite the progress of the road project north of Ba Ria Hospital, specifically the section passing through Long Tam ward, Ba Ria City.

The project was approved by the People's Committee of Ba Ria - Vung Tau province on October 31, 2016. The People's Committee of Ba Ria City issued administrative documents regarding land acquisition, compensation, support, and resettlement plans in accordance with the procedures stipulated by law for households affected by the land acquisition for the project. The total area of ​​land to be acquired for the project is over 21,853 m2. The total number of affected households is 11.

Mr. Dung affirmed that the People's Committee of Ba Ria City has approved all compensation and support plans for the 11 cases affected by the project in accordance with the correct procedures; resolving support policies for households whose assets are being expropriated on the land being reclaimed in accordance with regulations, creating favorable conditions for households subject to land clearance to stabilize their lives. The support policies ensure the legitimate rights and interests of the affected households.

Reasons for the delay in the multi-billion VND road project in Ba Ria - Vung Tau (image 1)

Ba Ria City will enforce land reclamation for the road project north of Ba Ria Hospital. Photo: TTCS.

To date, 10 households have complied with the land handover regulations, while one household with an area of ​​over 1,173 m2 has yet to hand over the land. To secure the land for the project, the People's Committee of Ba Ria City has established a mobilization team, which has repeatedly met with, held dialogues with, and campaigned to persuade the aforementioned household to comply with the land handover for construction.

However, to date, the household in question has remained uncooperative, refusing to comply and demanding other rights, such as filing complaints to claim benefits beyond those stipulated by the State, and requesting a review of the compensation policy…

The project for the road north of Ba Ria Hospital is invested by the People's Committee of Ba Ria City with a total investment of 110 billion VND. The project started in December 2021 and was expected to be completed after 2 years, but it is still facing land acquisition issues.

To definitively resolve the land acquisition issue and hand over the construction site on schedule, the People's Committee of Ba Ria City issued a decision to forcibly acquire land from Ms. Duong Thi Bi's household (Bac 1 Hamlet, Hoa Long Commune, Ba Ria City).

The enforcement decision has been delivered to the household and publicly posted. Simultaneously, the People's Committee of Ba Ria City has issued a decision establishing a Land Reclamation Enforcement Committee to implement the project; and continues to direct the Mobilization Team to educate and persuade Ms. Bi's household to comply with the handover of the land.

Currently, the People's Committee of Ba Ria City is also developing a plan to forcibly reclaim land to implement the project in accordance with regulations.

Hanoi explains why two general hospitals are behind schedule.

Hanoi explains why two general hospitals are behind schedule.

Despite repeated commitments, why are the two waste treatment projects in southern Hanoi still behind schedule?

Despite repeated commitments, why are the two waste treatment projects in southern Hanoi still behind schedule?

The Chau Doc - Can Tho - Soc Trang expressway project is behind schedule.

The Chau Doc – Can Tho – Soc Trang expressway project is behind schedule.

Many construction projects are behind schedule, hindering drainage.

Many construction projects are behind schedule, hindering drainage.

Duy Quang

Source: https://tienphong.vn/ly-do-duong-tram-ty-dong-o-ba-ria-vung-tau-cham-tien-do-post1660726.tpo


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Di sản

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Morning in Mo Si San

Morning in Mo Si San

Sunrise over my homeland

Sunrise over my homeland

Happy graduation day!

Happy graduation day!