Regarding the case of the prolonged Le Quang Dao Street project invested by the People's Committee of Nam Tu Liem District, Hanoi City, with signs of careless construction in some items, discussed with Traffic Newspaper reporter, Deputy Director Project Management Board (Project Management) of Nam Tu Liem District Nguyen Duy Trinh said that Inspectors of Hanoi Department of Transport (DOT) came to work and check quality, environment and safety assurance. traffic at the project.
“After Traffic Newspaper reported, yesterday (March 25), the Hanoi Department of Transport led by the Deputy Chief Inspector came to the project to work and check the quality and environmental assurance, work to ensure labor safety and ensure traffic safety at the project.
We have required construction units and construction supervisors to ensure the quality of the project. Along with that, we ensure environmental, labor safety and traffic safety when implementing the project," Mr. Trinh informed.
Commenting on the quality of the project, a construction quality management expert was surprised by the answer "it's just not good in terms of aesthetics" from the Nam Tu Liem District Project Management Board.
Talking about the perforated manholes in the project, this expert said that if in the design there is a sewer leading water into the manhole or an underground cable passing through, during the molding process, holes must be left to place the hole. sewer or run underground cables through.
“If the design had underground pipes and cables going through manholes, no one would have chiseled them like that. Doing so will not ensure structural quality. I was also very surprised by the authorities' explanation: "molding it like that to create adhesion", this person said.
Commenting on some pitted concrete light pole bases, this expert said that this is a sign of carelessness in construction.
“The picture shows only stone aggregate, without any cement water. Thus, all concrete structures like that do not ensure quality. This affects the quality of concrete, not just aesthetically. In these cases, it is necessary to demolish and rebuild, not just patch it with mortar and that's it," said this expert.
To ensure the quality of the project, this expert proposed that the State management agency for construction quality in Hanoi need to inspect the above phenomenon.
Talking about ensuring safety at a traffic construction project, especially a project with an intersection with a residential road, this expert said that along the construction route there must be signs about work safety. movement as well as a warning sign to let passersby know.
“In road construction, it is necessary to have HSET officers (H: health: health, S: safety: safety, E: environment: environment, T: transport: traffic). That means ensuring safety for workers, protecting the environment, ensuring internal traffic safety, as well as traffic safety for those using temporary roads," this expert said. .
“Make it messy to create adhesion”
Previously, reflecting to the Traffic Newspaper, readers said that the construction process of the Le Quang Dao street project was long (the section from Thang Long Avenue, Nam Tu Liem district to the boundary position with Duong Noi urban area). , Ha Dong district) causes dust, potentially unsafe for road users.
Present here in the middle of March 3, Traffic Newspaper reporter noticed that the project to build an extended Le Quang Dao street is under construction to the section crossing Dai Linh street.
Many construction vehicles and vehicles carrying construction materials regularly enter and exit the construction site, or cross Dai Linh Street to get to both sides of the construction site but are not warned or shielded to ensure safety.
“Trucks carrying construction materials and large-tonnage concrete enter and leave this construction site, but I don't see anyone guiding or regulating traffic. Furthermore, the intersection with Dai Linh street is not fenced, entry and exit are not managed," said Mr. Nguyen Van Huy, on Le Quang Dao street.
Not only that, during the process of entering and leaving the project, large trucks also carry mud, making Dai Linh street often dusty. This affects visibility, causing difficulties for motorcyclists and cyclists.
At the project site, reporters from Traffic Newspaper noted that some manholes were cracked and their necks were chipped. There are manholes that are chiselled or cut to fit drainage pipes, or to install cable systems.
Many concrete manhole necks were pitted so they were roughly patched with mortar. There is a manhole several meters deep, but there is only a rough warning with a few dry sticks.
Some light column bases also show signs of pitting and uneven concrete. Along with that, some parts of the project's concrete pavement line also showed signs of poor connection.
The mortar connecting the tiles and concrete of the sidewalk is also very thin. The process of constructing the concrete sidewalk was done poorly by workers. Some places had lost edges and were not square.
Explaining this incident, the Construction Investment Project Management Board of Nam Tu Liem district said that the above problems are "only not good in terms of aesthetics" but the quality is absolutely guaranteed.
Specifically, talking about manholes that are chiseled, the Construction Investment Project Management Board of Nam Tu Liem district said that such chiseling must be done to connect the underlying infrastructure.
"Making things like this is to create adhesion. Instead of casting squarely first, there will be no adhesion when installing sewers or installing underground cables through manholes," said Nam Tu District Construction Investment Project Management Board. Liem said.