Cao Lanh Expressway Construction

Báo Giao thôngBáo Giao thông23/12/2024

The Cao Lanh - An Huu Expressway Component 2 project through Dong Thap province is still stuck with land acquisition issues, causing difficulties for the contractor in construction.


Component 2 of the Cao Lanh - An Huu Expressway project started construction on August 27, 2024 and is expected to be completed and put into use on July 5, 2026. The project has a total length of about 11.43km, of which the section passing through Tien Giang province is 7.62km long, the rest is in Dong Thap province.

Thi công cao tốc Cao Lãnh - An Hữu vẫn gặp khó vướng mặt bằng- Ảnh 1.

Workers are busy constructing the Cao Lanh - An Huu expressway, component 2 project, section through Dong Thap province.

Major Nguyen Manh Hung - Director of Enterprise 98.2, Truong Son Construction Corporation (the contractor) said that the section through Dong Thap province is under the contractor's responsibility. This section is 3.8km long and passes through two districts, Thap Muoi and Cao Lanh.

Currently, at the construction site, to speed up construction progress, in early December, the contractor increased the number of workers by 30% and the number of machines and equipment by 50%.

Up to now, the construction progress of the two bridges, Canal 307 and Cai Lan, has basically met the investor's requirements. Regarding the road, the contractor is still facing difficulties due to land clearance problems.

Specifically, regarding technical infrastructure, the entire route has not been relocated according to regulations. Meanwhile, the project has affected more than 200 households. To date, two households in important locations have not yet handed over the site to the construction unit.

Thi công cao tốc Cao Lãnh - An Hữu vẫn gặp khó vướng mặt bằng- Ảnh 2.

Construction progress of bridges included in the basic package meets the investor's requirements.

The first location with land clearance problems is also the most important location at the intersection with provincial road (DT) 850. This is the location adjacent to component project 1 and component project 2.

The next location with land clearance problems is on public service road number 3. This location is still stuck, leading to many difficulties in assembling the contractor's machinery and equipment to organize the construction.

Regarding technical infrastructure, relevant units have planned to relocate but the specific time for handing over the clean site to the construction unit is unknown.

Mr. Huynh Xuan Binh, Director of the Land Fund Development Center of Dong Thap province, said that up to this point, the construction site of component project 2, Cao Lanh - An Huu expressway, the section passing through the province is basically favorable when all affected households have agreed on the compensation plan.

The remaining two households will also hand over the clean site to the construction unit in December, to ensure the project progress according to regulations.

The Cao Lanh - An Huu Expressway Component 2 project has a total length of about 11.43km. Of which, about 3.8km passes through Dong Thap province and more than 7.62km passes through Tien Giang province.
The project has a total investment of 3,856 billion VND, with Tien Giang People's Committee as the managing agency, starting at the intersection with component project 1, Cao Lanh - An Huu expressway at Km16 in My Hiep commune, Cao Lanh district (Dong Thap).
The end point of the project intersects with the Trung Luong - My Thuan expressway project at Km 98+950, about 1.8km from An Thai Trung intersection, An Thai Trung commune, Cai Be district (Tien Giang).



Source: https://www.baogiaothong.vn/thi-cong-cao-toc-cao-lanh-an-huu-van-gap-kho-vuong-mat-bang-192241223181112326.htm

Comment (0)

No data
No data
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony

Heritage

Figure

Business

No videos available

News

Political System

Local

Product