Highway 28B upgrade project at risk of stopping construction

The Ministry of Construction has sent a document to the People's Committee of Lam Dong province to speed up the site clearance progress of the project to renovate and upgrade National Highway 28B passing through the area.

Báo Lâm ĐồngBáo Lâm Đồng30/07/2025

The Ministry of Construction has sent a document to the People's Committee of Lam Dong province to speed up the site clearance progress of the project to renovate and upgrade National Highway 28B passing through the area.

According to the Vietnam Road Administration (Project Investor), up to now, the locality has handed over 61.7km/68km of land to the project, reaching 91% for construction. However, there are still 6.3km that have not been handed over. Some technical infrastructure works have not been relocated, such as 4.3km of water pipes, 100 electric poles of various types and railway signal lines at pier M2 of the railway overpass. In addition, the current land acquisition procedure still has 23.21ha of land clearance plan that has not been approved.

db80bce81643a01df952.jpg
National Highway 28B Project.

Due to the completion progress of the National Highway 28B project in 2025, there are only 5 months left to construct the project and disburse all the capital allocated in the medium-term public investment plan for the period 2021-2025.

img-8545-6821.jpg
National Highway 28B project passes through Phan Son commune.

Therefore, the Ministry of Construction requested the People's Committee of Lam Dong province to direct the People's Committees of communes and functional units to focus on completing compensation procedures, land recovery, and relocation of technical infrastructure systems in August so that contractors have a clean site to carry out construction.

In addition, the province will soon announce the focal point to perform the functions and tasks of the investor of the sub-project of site clearance for the National Highway 28B project.

img-8551-6980.jpg
Construction unit on Highway 28B.

The Ministry of Construction assigned the Vietnam Road Administration and Project Management Board 5 to closely coordinate with relevant agencies and communes of Lam Dong province to resolve problems in site clearance and construction, ensuring project completion in 2025.

In case the locality fails to complete the handover of the site according to the above progress milestone, the project will hardly be able to meet the completion schedule in 2025 and disburse all the capital allocated in the medium-term public investment plan for the period 2021-2025, and there is a risk that the implementation will have to be stopped and the capital will be adjusted to focus on key national projects, according to the direction of the Prime Minister .

Source: https://baolamdong.vn/du-an-nang-cap-quoc-lo-28b-co-nguy-co-dung-thi-cong-384392.html


Comment (0)

No data
No data
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together

Heritage

Figure

Business

No videos available

News

Political System

Local

Product