Complete land acquisition and clearance for Tam Trinh road expansion project in September

Báo Giao thôngBáo Giao thông01/09/2024


The investment project to build Tam Trinh Street, over 3.5km long, was approved by the Hanoi People's Committee in 2012, started in 2016, and is expected to be completed after 3 years. The project will widen Tam Trinh Street to 40m with 6 lanes. The project starts at Minh Khai Street, part of Ring Road 2 (nearly 44km long) and Ring Road 3 (65km long).

In 2012, the project had a total investment of VND 2,066 billion, and in 2019 it was adjusted to VND 3,354 billion. However, after 12 years, the project is still unfinished.

Hoàn thành GPMB dự án mở rộng đường Tam Trinh trong tháng 9- Ảnh 1.

Tam Trinh Street has been flooded for many years, making it difficult for people to travel.

Regarding the implementation status of the Tam Trinh road construction project, the People's Committee of Hoang Mai district said that it is aiming to basically complete site clearance work by the end of September 2024, focusing on construction and striving to basically complete the Tam Trinh road expansion project by the end of 2025.

Hoang Mai District People's Committee also requested the District Land Fund Development Center to coordinate with the locality to complete site clearance for the project before October 1, 2024.

Up to now, the site clearance work in Mai Dong ward has been basically completed, especially the Mai Dong market area has been handed over. As for Yen So ward, the length of the project route running through the ward is 1.3km with a total recovered area of 43,000m2, involving 1,300 cases, of which 800 households are related to agricultural land, the rest is residential land.

Up to now, the West Tam Trinh area has completed land clearance, while the East Tam Trinh area involves 201 households, with 146 households not yet cleared. The Ward People's Committee has mobilized and propagated, up to now, there are still 40 households that have not agreed to the compensation plan.

Hoang Mai District People's Committee affirmed that although there are still many difficulties and problems that need to be resolved, the District People's Committee is determined to basically complete site clearance work by the end of September 2024, focus on construction and strive to basically complete the Tam Trinh road expansion project by the end of 2025.

Therefore, according to Hoang Mai district, the local government is making efforts to implement solutions for the locations with land acquisition problems. In particular, focusing on propaganda and mobilizing people in the project to hand over land to the project. In addition, because the 2023 Land Law has come into effect, a Council must be established to determine the first land registration. The Council will determine the purpose of land use of households, the duration of land use, and many other factors.



Source: https://www.baogiaothong.vn/hoan-thanh-gpmb-du-an-mo-rong-duong-tam-trinh-trong-thang-9-192240901083125607.htm

Comment (0)

No data
No data
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground
Watch helicopters rehearse in the sky of Hanoi in preparation for National Day September 2
U23 Vietnam radiantly brought home the Southeast Asian U23 Championship trophy
Northern islands are like 'rough gems', cheap seafood, 10 minutes by boat from the mainland
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together

Heritage

Figure

Business

No videos available

News

Political System

Local

Product