Many violations of environment and land
On August 27, the Inspectorate of the Department of Natural Resources and Environment of Dong Nai province concluded the compliance with the law on land, environmental protection and water resources for Cu Thanh Company Limited.
Cu Thanh Company Limited is headquartered at 108 National Highway 51, An Phuoc Commune, Long Thanh District. The company has 3 factories at the headquarters and 2 factories in Long Thanh Industrial Park and Nhon Trach 3 Industrial Park.
At the time of inspection, the company had 4,975 employees, including 3,115 at the headquarters factory, 1,500 at the Long Thanh Industrial Park factory and 360 at the Nhon Trach 3 Industrial Park factory.
The inspection conclusion clearly pointed out the violations of Cu Thanh Company Limited.
Regarding the factory at the headquarters, regarding environmental protection, the factory does not have a license under the licensing authority of the Provincial People's Committee. In 2021, the company invested in expansion, generating a total of 650 m3 of industrial wastewater per day and night (or 459,000 m3 of emissions per hour).
While the regulations state that a project that generates a total amount of industrial wastewater from 500 m3/day (24 hours) or from 20,000 m3 of emissions/hour or more, is required to prepare an environmental impact assessment report, now the environmental license is under the approval authority of the provincial People's Committee.
Regarding land use, the company has arbitrarily changed the purpose of use of 2,747.8m2 of perennial land to non- agricultural land (arranged for warehouses and motorbike parking lots) at plots 275, 283 and plots 81, 215, 240, 241 on map sheet 50 of An Phuoc commune. These plots of land have been signed by the People's Committee of Long Thanh district to issue land use right certificates to individuals. The company's arrangement for motorbike parking lots is based on the opinion of the People's Committee of An Phuoc commune in the working minutes dated August 5, 2022. Therefore, the company's use of this land is requested to be directed by the People's Committee of Long Thanh district to handle according to regulations.
Proposing Long Thanh District People's Committee to handle Cu Thanh Company Limited
In addition, the company also conducted incomplete monitoring of wastewater parameters; Incorrectly determined the volume of hazardous waste in the 2022 environmental protection work report compared to the records and documents provided by the company and reported to the inspection team....
The Inspectorate of the Department of Natural Resources and Environment of Dong Nai province requested the People's Committee of Long Thanh district to direct the People's Committee of An Phuoc commune and specialized agencies to consider and handle Cu Thanh Company Limited for using 2,747.8 m2 of land for the wrong purpose; strictly monitor and supervise the dismantling of temporary works on the land area of underground water supply pipeline and the area of 300 m2 of traffic land planning.
Propose Long Thanh District Electricity to inspect and have a plan to move the power station out of the traffic land area (at the dead-end alley located within the company fence).
The inspection team requested Cu Thanh Company Limited to immediately overcome the existing shortcomings and coordinate with the Department of Natural Resources and Environment Inspectorate to consider handling administrative violations against Cu Thanh Company Limited for environmental violations.
Source: https://laodong.vn/kinh-doanh/lo-nhieu-sai-pham-tai-cong-ty-gan-5000-lao-dong-o-dong-nai-1385547.ldo
Comment (0)