Identifying '6 clear' points in the disbursement of public investment capital in Dong Nai

(DN) - On the morning of August 10, in Binh Phuoc ward, Provincial Party Committee member, Vice Chairman of Dong Nai Provincial People's Committee Ho Van Ha chaired a conference on public investment disbursement in the northern region of Dong Nai province. Attending were leaders of provincial departments and branches, project owners and leaders of 40 communes and wards in the northern region of Dong Nai province.

Báo Đồng NaiBáo Đồng Nai10/08/2025

Vice Chairman of Dong Nai Provincial People's Committee Ho Van Ha speaks at the conference. Photo: Thanh Mang

According to the Department of Finance's report, as of August 7, the disbursement according to the capital plan was 8,835 billion VND out of the total allocated capital of 36,073 billion VND, reaching more than 34% of the total public investment plan of the whole province. In which, not including the capital allocated for the North - South Expressway Project, West section Gia Nghia (Dak Nong) - Chon Thanh ( Binh Phuoc ), which is 10,886 billion VND, allowed to be disbursed until 2026.

Leaders of Dong Nai Province Department of Finance report on disbursement progress and propose solutions. Photo: Thanh Mang

At the conference, the representative of the Department of Finance also pointed out the existing problems and difficulties of 11 Project Management Boards in the Northern Dong Nai region and Project Management Board of Region 09 (formerly Vinh Cuu district) that are implementing 68 projects; along with 295 public investment projects and 41 public capital projects (invested by the People's Committee at the district level) that have not yet submitted final settlement documents... At the same time, the investor is requested to proactively contact the Department of Construction to grasp the progress of processing adjustment documents and promptly complete the document adjustment procedures. Thereby, striving to successfully implement the "30 days and nights of public investment disbursement" launched by the Provincial People's Committee, by August 31, the disbursement reached more than 11,478 billion VND, equivalent to 55% of the total public investment capital plan assigned in 2025.

Leaders of departments and branches of Dong Nai province spoke at the conference. Photo: Thanh Mang
Leaders of departments and branches of Dong Nai province spoke at the conference. Photo: Thanh Mang
Investor representative speaks at the conference Photo: Thanh Mang
Investor representative speaks at the conference Photo: Thanh Mang

At the conference, representatives of leaders of departments, branches, and project management boards reported on the progress of projects and difficulties, and proposed solutions to the Provincial People's Committee for investors to implement in the coming time.

Representatives of leaders of communes and wards in the Northern Dong Nai region spoke at the conference. Photo: Thanh Mang

Speaking at the conference, Provincial Party Committee member, Vice Chairman of Dong Nai Provincial People's Committee Ho Van Ha assigned the Department of Finance to study current regulations and advise the Provincial People's Committee to decentralize to the Commune People's Committees to settle previously completed works and projects, ensuring the completion of the assigned task of disbursing the 2025 capital plan. He requested that the investor units must make a detailed disbursement plan for each project and work each week and the heads, including the People's Committees of wards and communes, must take full responsibility for the disbursement results according to the registered plan.

Vice Chairman of the Provincial People's Committee Ho Van Ha also requested departments and branches to promote their roles and responsibilities in the disbursement of public investment capital. Timely support and guide investors and localities to remove difficulties and obstacles in the process of disbursing public investment capital, especially those related to site clearance, progress and quality of projects. In particular, each officer and civil servant participating in public investment tasks must determine the "6 clear" motto including: clear person, clear work, clear time, clear responsibility, clear product, clear authority, as issued by the Provincial People's Committee to best perform the assigned disbursement task.

Thanh Mang - Ngoc Thao

Source: https://baodongnai.com.vn/kinh-te/202508/xac-dinh-6-ro-trong-cong-tac-giai-ngan-von-dau-tu-cong-cua-dong-nai-3550f09/


Comment (0)

No data
No data

Same tag

Same category

Spend millions to learn flower arrangement, find bonding experiences during Mid-Autumn Festival
There is a hill of purple Sim flowers in the sky of Son La
Lost in cloud hunting in Ta Xua
The beauty of Ha Long Bay has been recognized as a heritage site by UNESCO three times.

Same author

Heritage

;

Figure

;

Enterprise

;

No videos available

News

;

Political System

;

Destination

;

Product

;