The Management Board of Investment and Construction Projects for Transport and Agricultural Works of Da Nang City said that it has reported on the plan for site clearance and resettlement for people serving the North-South High-Speed Railway project.
Accordingly, the high-speed railway line on the North-South axis through Da Nang city is more than 116 km long, passing through 24 communes and wards of the city, starting at Hai Van ward, ending at Nui Thanh commune. On the line, there are 2 passenger stations: Da Nang station, Tam Ky station, 1 cargo station: Chu Lai station, 4 depots and maintenance stations...
After coordinating with units to review and investigate, the Management Board of Investment Projects for Construction of Traffic and Agricultural Works of Da Nang City said that the total land area recovered for the project through the city's territory is 843.55 hectares.
Of which, residential land is about 105.2 ha; rice land is about 225.67 ha; forest land is about 240.63 ha; other types of land such as agriculture, traffic, irrigation... are about 272.05 ha.
The high-speed railway line on the North-South axis through Da Nang city is more than 116 km long, passing through 24 communes and wards of the city. |
In addition, about 2,139 houses are affected, with a need for resettlement of about 3,148 lots. It is expected to build 35 resettlement areas to serve the project, with a total area of about 211.81 hectares and 3,316 resettlement lots.
Estimated cost of site clearance and resettlement, the Management Board of Investment Projects for Construction of Traffic and Agricultural Works of Da Nang City said that it needs about 16,600 billion VND. Of which, the North of Thu Bon River is 7,479 billion VND, the South of Thu Bon River is 9,120 billion VND.
Specifically, the cost of compensation and support is 12,907 billion VND; the cost of building resettlement areas is 3,692 billion VND...
The Prime Minister has directed localities where the project passes through to focus on directing the rapid implementation of site clearance and relocation of technical infrastructure works to meet the schedule for starting construction of the resettlement area on August 19, 2025.
The Management Board of Investment and Construction Projects for Traffic and Agricultural Works in Da Nang City said that the unit proposed to start construction of a resettlement area in Dien Ban Bac ward, with an area of 4.7 hectares, with 116 resettlement lots, with a total investment of about 91 billion VND.
The Management Board of Investment Projects for Construction of Traffic and Agricultural Works of Da Nang City proposed that the City direct relevant units to quickly implement site clearance and related procedures to start construction of the Resettlement Area on August 19, 2025 as directed by the Prime Minister.
In addition, direct localities along the route to urgently implement the work of reviewing cadastral data, initial inventory of land, assets on land, population... according to the project boundary. Develop a detailed plan for implementing compensation, support, and resettlement to serve the project...