The Government Office issued Notice 104 dated June 12, 2025, concluding the work of Permanent Deputy Prime Minister Nguyen Hoa Binh at the working session of Inspection Team No. 01 on removing difficulties and obstacles at 4 expressway projects: Hoa Lien - Tuy Loan, Quang Ngai - Hoai Nhon, Hoai Nhon - Quy Nhon and Quy Nhon - Chi Thanh.
In the above Notice, on behalf of the Government, the Inspection Delegation acknowledged and commended the Ministry of Construction , ministries, branches, localities, investors, and construction contractors for actively implementing their tasks, having many drastic and creative solutions in resolving existing problems and difficulties, and speeding up the progress of projects.
After nearly 3 months since the previous inspection, the agencies have completed a huge amount of work, most of the difficulties and obstacles have been resolved such as: basically completing the site clearance for projects in the provinces and cities of Da Nang , Binh Dinh, Phu Yen; increasing the capacity of Truong Ban quarry for Hoa Lien - Tuy Loan project; increasing the capacity of My Trang and Van Ly quarries and adding Pho Phong quarry for Quang Ngai - Hoai Nhon project...
The Deputy Prime Minister affirmed: The problems, obstacles, and delays in some projects are not major, mainly due to objective reasons related to site clearance. The inspection team believes that with the determination and efforts of agencies and units, the projects will be completed and put into operation in 2025 as set out, including many sections that can be inaugurated on August 19, 2025, the 80th anniversary of the August Revolution and National Day September 2. The Ministry of Construction reviewed and selected a number of projects to organize inauguration ceremonies on the above anniversaries in accordance with the direction of the Prime Minister in Official Dispatch No. 57 dated May 5, 2025.
Must ensure quality and labor safety according to regulations
The Deputy Prime Minister once again affirmed that the goal of synchronously completing projects in 2025 remains unchanged; in which it is necessary to ensure that most sections are completed in August and September 2025; particularly difficult sections and projects are completed before December 31, 2025.
To achieve this goal, the Deputy Prime Minister requested the People's Committee of Quang Ngai province to focus on resolving the site clearance work, ensuring the handover of all sites for project construction before June 15, 2025. Other localities need to resolve the existing problems and obstacles of the projects to focus resources on continuing to carry out other very large and important tasks in the coming time such as arranging the administrative apparatus when merging provinces, implementing large-scale, nationally important projects in the provinces such as the North-South high-speed railway project, the Quang Ngai - Kon Tum, Quy Nhon - PleiKu expressway projects, etc.
The Ministry of Construction is responsible for strengthening inspection, supervision, and directing investors and contractors to increase human resources, equipment, proactively gather supplies, materials, financial resources, etc., organize construction in 3 shifts, 4 teams, and work on holidays and days off to complete according to the committed schedule; note that quality, environmental sanitation, and labor safety must be ensured in accordance with regulations, and not be ignored or shortened for the sake of progress, or choose materials that do not meet standards, causing environmental pollution, or labor safety at the construction site.... Review and accelerate the implementation of the system of rest stops, traffic monitoring systems, toll collection, and vehicle load control, ensuring that projects put into operation must be synchronous, of high quality, aesthetically pleasing, worthy of being typical works and projects of the transport sector, meeting the needs and expectations of the people and society.
The Ministry of Finance and the Ministry of Construction review the allocated capital sources, acceptance procedures, and payment of projects to create the most favorable financial resources for contractors to implement projects.
The Deputy Prime Minister requested ministries, agencies and localities to consider this a top priority political task, requiring the drastic and synchronous participation of the entire political system; proactively upholding personal responsibility, responsibility to the collective, putting national interests first, meeting the expectations of the people and the business community.
The Ministry of Construction, as both the standing agency of the Inspection Team and the project management agency, continues to direct, monitor, and coordinate with the Government Office to urge assigned tasks, promptly synthesize and report to competent authorities to resolve difficulties and problems, ensuring that all 4 projects are completed in 2025 according to the set goals.
Source: https://baophapluat.vn/chinh-phu-chi-dao-hoan-thanh-dong-bo-4-du-an-cao-toc-trong-nam-2025-post551621.html