According to the report at the meeting, all maintenance work is being urgently deployed with the goal of completion before October 31, 2025. Key items, especially in the power - steam workshop, are being prioritized. The main power station has been completed and put into operation, ensuring stable power supply for the entire factory. Progress is being controlled every day, mobilizing maximum human resources and equipment to meet the plan.
Speaking at the meeting, BSR Chairman Bui Ngoc Duong emphasized that the restart of Dung Quat Biofuel Plant is a strategic task, closely linked to the green transformation orientation of Petrovietnam and BSR. Mr. Bui Ngoc Duong requested the units to focus highly and coordinate closely to ensure progress while strictly following safety and quality procedures to put the plant into operation as planned, contributing to the stable supply of biofuel to the market and affirming the pioneering role in clean energy development.
When it resumes operations, Dung Quat Biofuel Plant will join Dung Quat Oil Refinery to form a synchronous production and supply chain, meeting domestic biofuel demand. This is not only an important step in the green energy transition roadmap but also affirms BSR's determination to develop sustainably, be environmentally friendly and make practical contributions to national energy security.
Hieu Linh
Source: https://bsr.com.vn/web/bsr/-/chu-tich-hdqt-bsr-ra-soat-tong-the-cong-tac-tai-khoi-dong-nha-may-nlsh-dung-quat
Comment (0)