Representative of the Construction Investment Project Management Board No. 2, Mr. Phan Duc Thanh, reported a summary of the project implementation. Accordingly, the project with a scale of 30.08 hectares will invest in the construction of the following items: Observatory, square, outdoor stage; camping area, rest hut; planting trees on water surface, construction of high and low roads; reinforcement of canal embankments; construction of boat docks.
Hung Vuong Park project combines the park perimeter with the riverside promenade, expanding Ton That Tung and Le Dai Hanh streets in the area to serve visitors.
The total investment of the project is 498 billion VND. Currently, the Construction Investment Project Management Board No. 2 has implemented the investment preparation phase such as approving the design, estimate, contractor selection plan, etc.
Meanwhile, recently, the compensation and site clearance work for the Hung Vuong Park Project was carried out by the Binh Thuan Land Fund Development Center (formerly) at the Hung Vuong Residential Area Phase II project, area 4 + 5 in the new Phu Thuy ward, with a total area of over 43 hectares, and a total of 124 households receiving compensation.
To date, there have been decisions on compensation and support for 109 files, covering an area of over 33 hectares. The remaining files are being negotiated for compensation and site clearance by the Lam Dong Provincial Land Fund Development Center after the merger.
At the meeting, functional departments and branches expressed their opinions and requested the Management Board of Construction Investment Project No. 2 and the Land Fund Development Center of Lam Dong province to remove obstacles and speed up the project's construction progress.

After listening to opinions from units, Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh said that the implementation of work in the past time was still slow.
In the coming time, relevant units need to promptly implement assigned tasks to speed up project implementation progress.
Vice Chairman of Lam Dong Provincial People's Committee Nguyen Minh
The Vice Chairman of the Provincial People's Committee requested the Management Board of Construction Investment Project No. 2 to coordinate with functional units to base on specific urban planning to re-determine and adjust the detailed planning of the project; ensure connection with the surrounding natural landscape, create harmony, and ensure environmental sanitation.
.jpg)
The Department of Construction is responsible for appraising the project design. Along with that, the Department of Finance advises the Provincial People's Committee to arrange funds to pay for planning costs for the consulting unit.
The Department of Agriculture and Environment reviewed and handed over the compensation and site clearance dossiers to the Lam Dong Provincial Land Fund Development Center so that the center could coordinate with Phu Thuy Ward to carry out propaganda and mobilize people in compensation and site clearance for the remaining dossiers, and support resettlement for households in the project area.
The locality does not allow encroachment or re-encroachment in the project area...
Source: https://baolamdong.vn/day-nhanh-tien-do-du-an-cong-vien-sinh-thai-hung-vuong-387790.html