BPO - On the afternoon of January 23, Binh Phuoc Power Company temporarily energized 2 circuits from the 171 and 172 outfalls of Phuoc Long 220kV transformer station (Bu Nho commune, Phu Rieng district) to the connection point with the existing Phuoc Long - Vedan 2 110kV line. This is phase 1 of the 110kV outfall project from Phuoc Long 220kV 4-circuit station implemented by the unit.
Deputy General Director of Southern Power Corporation Doan Duc Hung came to congratulate and encourage officers and construction workers of Binh Phuoc Power Company.
Deputy General Director of Southern Power Corporation Doan Duc Hung (in plaid shirt) congratulated and encouraged officers and construction workers of Binh Phuoc Power Company.
During the implementation process, Binh Phuoc Electricity Company has closely coordinated with related units to ensure labor safety, construction progress and project quality.
Phase 2 of the project will energize the remaining 2 circuits from the exposed compartment to the Phuoc Long 220kV station to the connection point with the Phuoc Long - Dong Xoai 110kV line under construction with 13 pole positions. Binh Phuoc Power Company will make every effort and determination to implement the project on schedule.
The entire 2.55km long 4-circuit line project, with a total investment of 30.66 billion VND, was implemented by Binh Phuoc Electricity Company. This project is implemented with the goal of transmitting power from Phuoc Long 220kV station to the existing Phuoc Long, Dong Xoai, Dong Phu, Vedan 2, Bu Dang 110kV stations and the newly constructed Bac Dong Phu and Phu Rieng Industrial Park 110kV stations; creating a 110kV loop connecting Phuoc Long, Binh Long 2 220kV stations and Thac Mo Hydropower Plant. Thereby, contributing to increasing transmission capacity, minimizing power outages, meeting the increasing electricity demand of people and businesses in the province.
Provincial electricity workers are completing the final stage of the 110kV line.
A corner of Phuoc Long 220kV transformer station and 110kV power line tower phase 1 of the project
Source: https://baobinhphuoc.com.vn/news/4/168393/dong-dien-duong-day-2-mach-110kv-tu-tram-220kv-phuoc-long