On July 24, 2025, in Phu Tho , the Party Committee of the National Power Transmission Corporation (EVNNPT), the Party Committee of the Northern Power Project Management Board (NPMB) held a ceremony to attach a signboard to welcome the 4th Congress of the Party Committee of Vietnam Electricity Group (EVN), term 2025-2030 with the Vinh Yen 500kV Transformer Station and connecting line project.
Efforts to bring the project to the finish line to meet schedule
The Vinh Yen 500 kV Transformer Station and connecting line project has a total investment of more than 860 billion VND. It is a special-class, group B energy project invested by EVNNPT, NPMB is assigned to manage and operate the project, Power Construction Consulting Joint Stock Company 3 designs, and Power Transmission Company 1 takes over and operates.
Comrade Nguyen Huu Tuan, Standing Deputy Secretary of the EVN Party Committee (right) presented the Decision to recognize the Project to welcome the 4th Party Congress of Vietnam Electricity Group, term 2025-2030. |
The 500 kV Vinh Yen transformer station and connecting lines were built in Trung My commune, Binh Xuyen district, Vinh Phuc province (old), now Binh Tuyen commune, Phu Tho province.
The project has a scale of building a new 500/220/35kV transformer station including 2 900MVA transformers, each transformer is connected to a combination of 3 single-phase transformers, capacity 300MVA; building 500kV and 220kV feeder compartments; building 2 connecting lines 4.7 km long.
Mr. Phung Bao Anh, Deputy Head of the Northern Power Project Management Board, said that the project implementation process encountered many challenges in site clearance compensation, resettlement arrangements for households, high fluctuations in material prices, and difficulties in mobilizing construction workers by contractors because EVN and EVNNPT were simultaneously implementing many key power projects...
The Vinh Yen 500kV Transformer Station site has many projects being implemented at the same time, many contractors participating in the bidding packages, leading to an impact on the progress of some items of the project. Along with that, in mid-May 2025, the new transformer was delivered to the station, so the unit coordinated with contractors to focus on working day and night to install and test and calibrate.
However, with the support and close direction of the local government, the Party Committee, the leaders and the Boards of the Group, the leaders of EVNNPT and NPMB are regularly present at the construction site to urge and remove obstacles in the construction of detailed progress and construction plans for the items, along with the high determination of the contractors participating in the construction to complete the energization and put into operation of the 500kV Vinh Yen Transformer Station on July 21, 2025, meeting the set schedule.
Delegates performed the ceremony of attaching the construction sign. |
The 500 kV Vinh Yen transformer station and connecting line, when completed, will be connected to the 500 kV Hiep Hoa - Son La and Hiep Hoa - Viet Tri lines, which will be the transfer point between two sources of thermal power and hydropower - from Son La and Lai Chau hydropower plants and thermal power clusters in the Quang Ninh area.
The transformer station will also be connected to the 500 kV Lao Cai - Vinh Yen line after the line is completed, promptly releasing power from small hydropower plants in the Northwest region and importing electricity, contributing significantly to ensuring electricity in the Northern region in the following years.
The project, once completed, is of great significance in meeting the growing load demand of the Phu Tho province power system; creating strong links between regions in the power system, increasing the ability to operate safely and stably for the national power system.
Continue to promote spirit to complete assigned projects
Speaking at the ceremony, comrade Nguyen Huu Tuan - Standing Deputy Secretary of the Party Committee of the Group warmly praised and congratulated the collective leadership, officers, engineers, workers of EVNNPT, NPMB, consulting units, contractors, functional agencies, authorities and local people where the project passed through for joining hands, being unanimous, united, and making efforts to overcome all difficulties, bringing the project to completion on schedule, ensuring quality, safety and efficiency.
Leaders of the Party Committee and Vietnam Electricity Trade Union awarded prizes to units that excellently completed the tasks in constructing the Vinh Yen 500kV Transformer Station Project and connecting lines. |
In the past time, under the leadership of the Party Committee, the entire Group has overcome difficulties and challenges, energized many power projects and completed energizing 681 power grid projects from 110-500 kV in the 2020-2025 term, contributing to the Group's basic assurance of electricity supply to serve the country's socio-economic development, including the Vinh Yen 500 kV Transformer Station Project and connecting lines.
The completion of the 500 kV Vinh Yen Transformer Station and connecting line project is the result of the emulation movement of laborers successfully completing all assigned tasks to which the labor force of EVN in general and EVNNPT, NPMB in particular have contributed with all their intelligence and capacity.
The installation of the project sign today is not only an event of encouragement and recognition of the enthusiastic and creative work of the staff, but also an important event affirming the organizational, management, construction capacity and the courage to overcome difficulties of EVN and EVNNPT in the period of strong transformation to firmly enter a new term with many great expectations.
Panorama of 500 kV Vinh Yen transformer station. |
Speaking at the ceremony, Comrade Nguyen Tuan Tung, Party Secretary, Chairman of the Board of Directors of EVNNPT said that the Project was honored to be recognized by the Party Committee of the Group to be a project to welcome the 4th Party Congress of the Group, term 2025 - 2030 and was launched by the Vietnam General Confederation of Labor to compete with the highest efforts to complete the construction progress and ensure the quality of the project.
In the coming time, EVNNPT will have to complete many key and urgent projects under the direction of the Prime Minister and the Group with large construction investment volume. Therefore, EVNNPT and its affiliated units will continue to strive to complete all planned tasks assigned by the Group. At the same time, the Party Committee of the Corporation hopes to continue to receive the attention and direction of the leaders of the Party Committee of the Group, the Group's specialized departments, and the joint efforts and support of local authorities so that EVNNPT can complete its assigned tasks, contributing to ensuring the country's energy security.