On June 7, the Provincial People's Committee had a meeting with a delegation of the World Bank (WB) to review the progress of the implementation of the Integrated Dynamic Urban Development Project in Ho Chi Minh City. Thai Nguyen. Mr. Le Quang Tien, Vice Chairman of the Provincial People's Committee, chaired the meeting and worked; Attending were leaders of a number of relevant departments and branches of the province and the City People's Committee. Thai Nguyen.
Work session scene. |
At the meeting, after hearing information about the project implementation progress, the World Bank representative highly appreciated Thai Nguyen province and Ho Chi Minh City. Thai Nguyen in leading, directing and implementing the Project, completing the contents beyond the set plan.
Regarding the implementation progress of the Project, up to now, with 9 work items (Component 1 – Structure investment, upgrading, improvement and construction of urban infrastructure), 4 items have been completed. , put into use from 2022; The remaining 5 items are completed with a workload of 70-90%.
For financial work, accumulated loan capital so far is over VND 945 billion, accounting for 73,7% of total loans; accumulated disbursement of counterpart funds is over 714 billion dong, reaching 73,8% of total counterpart capital.
In Component 2 – Non-structural investment, technical assistance and implementation support, 4/11 bidding packages have been completed, 7 bidding packages are being implemented, with the completion volume reaching 70-97%. It is expected that all items of the Project will be completed in September 9.
The Huong Thuong Bridge project has been completed over 80% of the work volume. |
At the meeting, on the basis of the request of the delegation, representatives of departments and branches of the province and city. Thai Nguyen clarified the contents related to environmental management; ensure labor safety; site clearance work; implementation of the recommendations of the World Bank…
Agreeing with the contents and issues proposed by the World Bank, Vice Chairman of the Provincial People's Committee Le Quang Tien asked the relevant departments and branches of the province to closely coordinate with the City People's Committee. Thai Nguyen continues to perform well the compensation and site clearance work; speed up the appraisal of the explained contents; coordinate and guide the implementation of inspection and acceptance when the work items are completed in order to speed up the disbursement and settlement according to the plan...
The Dynamic Urban Integrated Development Project of Ho Chi Minh City. Thai Nguyen has a total investment of 2.250 billion VND. In which, the loan from the World Bank is over VND 1.282 billion, the rest is local counterpart capital. The project started in 2018 and is expected to be completed in 2023.
|