Dai Ngai 2 Bridge closed 7 months ahead of schedule

Báo Giao thôngBáo Giao thông05/01/2025

Dai Ngai 2 Bridge across Hau River, connecting Cu Lao Dung district with Long Phu district ( Soc Trang province) officially closed after more than 1 year of construction.


On the morning of January 5, Project Management Board 85 ( Ministry of Transport ) held a closing ceremony for the Dai Ngai 2 Bridge Construction Project - Package No. 11-XL (crossing the Hau River, connecting Cu Lao Dung District with Long Phu District, Soc Trang Province).

Hợp long cầu Đại Ngãi 2 vượt tiến độ 7 tháng- Ảnh 1.

Delegates conduct the closing ceremony.

Mr. Le Dinh Thong, Director of Project Management Board 85, said that the project was approved by the Ministry of Transport on December 23, 2022.

This is a group A project, a special-grade road traffic project with a total investment of 7,962.148 billion VND, the investment capital is from the State budget.

Dai Ngai 2 Bridge Project has a total route length of more than 15km, the starting point of the project intersects with National Highway 54, in Hung Hoa Commune (Tieu Can District, Tra Vinh Province), the end point intersects with Nam Song Hau National Highway, in Long Duc Commune (Long Phu District, Soc Trang Province).

Hợp long cầu Đại Ngãi 2 vượt tiến độ 7 tháng- Ảnh 2.

Dai Ngai 2 Bridge was completed 7 months ahead of schedule.

The bridge is 862m long, with a total of 13 spans, with 91 bridge girders (each girder weighs more than 80 tons, nearly 40m long). The main span, 330m long, is constructed as a cantilever structure.

Up to now, all 46/46 cantilever segments have been completed, 49/91 girder slabs have been installed, 8/13 super-T girder spans have been constructed, and the project has basically been opened to traffic on April 30, 2025.

Dai Ngai 2 Bridge, when completed, will connect Cu Lao Dung island district with the mainland, breaking the isolation of this land in the middle of Hau River.

Hợp long cầu Đại Ngãi 2 vượt tiến độ 7 tháng- Ảnh 3.

Construction progress of the entire project is about 60%.

Speaking at the closing ceremony, Mr. Lam Van Man, Secretary of Soc Trang Provincial Party Committee, highly appreciated the efforts of Project Management Board 85, the contractor and construction units who made great efforts to close Dai Ngai 2 Bridge 7 months ahead of schedule compared to the original plan.

At the same time, he requested that units continue to focus on human resources and equipment to speed up progress to open the road to traffic on April 30, 2025 as committed.



Source: https://www.baogiaothong.vn/hop-long-cau-dai-ngai-2-vuot-tien-do-7-thang-192250105111417822.htm

Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product