According to the decision, Lao Cai province maintains the scope and scale of investment in phase 1 that was previously approved. Specifically, in this phase, Sa Pa Airport will be built to meet the standards of a level 4C airport according to the classification of the International Civil Aviation Organization (ICAO), with a designed capacity of 1.5 million passengers/year, while ensuring the function of a level II military airport.
The new point of this decision is the addition of the content to complete the items of phase 2, aiming to increase the port's operating capacity to 3 million passengers/year, in line with the development plan.
The additional items include: completing the construction of two taxiways connecting terminal 14, adding a parallel taxiway connecting terminal 14 to the aircraft parking lot (23m wide), adding three parking positions for Code C aircraft and equivalent, expanding the passenger terminal (reaching a capacity of 3 million passengers/year over two phases), arranging a telescopic bridge to pick up and drop off passengers, etc.
Component project 2 has a contract term of 46 years and 7 months, of which: time for establishing, appraising technical design, designing construction drawings, and organizing contractor selection is 1 year; construction time for phase 1 is 2 years and 1 month; operation, exploitation and capital recovery time is 43 years and 6 months.
Phase 2 is implemented during the operation and exploitation period without affecting the project's financial plan.
The total investment of Component Project 2 is 6,393,845 billion VND (including VAT), of which: phase 1 is 3,982,122 billion VND and phase 2 is 2,411,723 billion VND.
Capital structure includes: equity and loan capital of VND 3,537,946 billion; State capital in the PPP project is VND 2,855,899 billion, accounting for 44.38% of total investment.
The form of investor selection is open domestic bidding, without pre-selection, with the expected selection time from the third quarter of 2025. Lao Cai Provincial People's Committee assigned Lao Cai Provincial Department of Construction to be the inviting party, responsible for presiding over and coordinating with relevant agencies to complete the bidding documents, submit to competent authorities for approval, as a basis for organizing the selection of investors in accordance with legal regulations.