Delaying the operation time of the Nhon - Hanoi station metro line

Đảng Cộng SảnĐảng Cộng Sản13/03/2023


On March 13, the Hanoi People's Committee sent a document to the Prime Minister requesting to adjust the time to put into operation the elevated section of the Nhon - Hanoi Railway Station urban railway project into August this year, instead of the end of 2022 as planned.

Accordingly, to commercially exploit the elevated section of the Nhon - Hanoi Railway Station metro project, the city plans to complete the CP5 package at the Depot area in May 2023 and the work group for acceptance, handover and system safety certification in August 2023.

At the same time, relevant units also organized a trial operation phase for 57 operation and maintenance scenarios according to the train schedule of 3 shifts/day, 7 days/week, this period is expected to last for 8 weeks, starting from May 2023 to June 2023.

Previously, in August 2022, during a working session with Hanoi City and related units, the Prime Minister requested the completion of the elevated section of the Nhon - Hanoi Railway Station by the end of 2022 and to study and find solutions to shorten at least half the time to complete the underground section compared to the consultant's proposal of 2027.

It is known that the Nhon - Hanoi Railway Station metro line started construction in September 2010 with a total investment of 18,408 billion VND and is expected to be completed in 2016. The length of this urban railway line is 12.5km; including 8.5km above ground and 4km underground. It passes through the districts: Bac Tu Liem, Nam Tu Liem, Cau Giay, Ba Dinh, Dong Da, Hoan Kiem. The Deport is located in Nhon with an area of ​​15ha.

However, after 13 years of implementation, the project progress has only reached about 75% and the total investment has increased from more than 18,000 billion VND to more than 34,000 billion VND.

According to the Master Plan for Capital Construction to 2030 and vision to 2050, the urban railway network includes 8 lines with a total length of 318km.

- Route 1: Ngoc Hoi - Yen Vien - Nhu Quynh, about 38.7km long.

- Line 2: Noi Bai - City Center - Thuong Dinh, 35.2km long, is the backbone for the current and future urban area, connecting with line 2A.

- Line 3: Nhon - Hanoi station - Hoang Mai is 21km long. After 2020, line 3 will be developed to Son Tay, with a total expected length of 48km.

- Route No. 4: Dong Anh - Sai Dong - Vinh Tuy/Hoang Mai - Thanh Xuan - Bac Tu Liem - Thuong Cat - Me Linh. The route is 53.1km long, circular in shape, connecting with routes No. 1, 2, 3 and 5.

- Line 5: South West Lake - Ngoc Khanh - Lang - Hoa Lac, 34.5km long.

- Line 6: Noi Bai - New urban area west of Ngoc Hoi, connecting with line 4 at Co Nhue and line 7 at Duong Noi, 43km long.

- Line 7: Me Linh - New urban area in the West of Nhon - Van Canh - Duong Noi, connecting with line 4 at Dai Mach and Tay Tuu sections, with line 6 at Duong Noi section, about 35km long.

- Route 8: Co Nhue - Ring Road 3 - Linh Nam - Bat Trang - Duong Xa, about 28km long.



Source link

Comment (0)

No data
No data

Same category

Su 30-MK2 fighter jets drop jamming shells, helicopters raise flags in the capital's sky
Feast your eyes on the Su-30MK2 fighter jet dropping a glowing heat trap in the sky of the capital
(Live) General rehearsal of the celebration, parade, and march to celebrate National Day September 2
Duong Hoang Yen sings a cappella "Fatherland in the Sunlight" causing strong emotions

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product