HomeNewsEconomyPhu Yen strives to hand over 4% of the premises by the end of April...

Phu Yen strives to hand over 4% of the North-South expressway project site by the end of April


Phu Yen strives to hand over 4% of the North-South expressway project site by the end of April

The component project of the Quy Nhon - Chi Thanh section, part of the North-South Expressway Project running through Phu Yen province, still has land problems, so the province aims to hand over it by the end of April 4. premises for investors.





The North - South Expressway project, the Quy Nhon - Chi Thanh section through Phu Yen province, still has land problems, mainly residential houses.

The compensation price has not been agreed upon

Song Cau Town is one of the localities in Phu Yen province that has a Quy Nhon - Chi Thanh section project running through the North - South Expressway Project. However, the section through the town still has land, mainly residential houses.

Currently, this locality still has 36 households that have not yet handed over their premises, mainly houses. Song Cau town built 5 resettlement areas for people to clear to build the North-South expressway, but so far only 3 resettlement areas have been completed, the remaining 2 areas are continuing construction.

Mr. Le Xuan Hien, Deputy Director in charge of Song Cau Town Land Fund Development Center, said that currently, some people in the area of ​​clearance have not yet agreed with the compensation price and have not received compensation.

According to Mr. Hien, there are many reasons leading to the slow completion of expressway clearance, including the number of households affected is very large, about 1200 households.





The construction contractor is speeding up the progress of the project.

“Currently, in Song Cau town, especially in Xuan Loc commune, there are still problems, mainly households, the number of houses affected is very large. Another reason is the origin of the land. Previously, during the management process, some households used it for improper purposes, so the process of reviewing and investigating documents led to delays," Mr. Le said. Xuan Hien said.

The North-South expressway project through Phu Yen province has a length of more than 90 km, so far only 88,42 km has been handed over. Tuy An districts, Dong Hoa town, Song Cau town have not yet completed site clearance and have been late many times. The reason for the delay in handing over the site is that there is no resettlement land, slow approval of the site clearance plan, and organizing a lottery for resettlement land for households to clear...

Focus on solving the problem completely

Mr. Le Tan Ho, Vice Chairman of the People's Committee of Phu Yen province, requested the Chairman of the People's Committees of districts, towns and cities in the province to urgently complete the resettlement areas, ensuring the handover of the premises on time.

In addition, Mr. Ho also emphasized that the heads of localities are fully responsible to the Provincial People's Committee if there is a delay in progress as required.

“By March 31, Song Cau town must hand over the entire premises. Now there is another problem: the technical infrastructure, mainly electricity. For the electrical system that still has problems, it can be constructed, but it's still difficult for you to do, making it difficult to be proactive. It is expected that by the end of April 3, we will have to hand over all the premises to investors. It may be slow, but we will try our best because the start is too slow," said Mr. Le Tan Ho.

At a recent actual inspection of the implementation of the North-South Expressway through Phu Yen province, Minister of Transport Nguyen Van Thang said that currently, Phu Yen province has the largest land problem in two areas. The weak soil is Xuan Loc commune, Song Cau town and Ky Lo bridge area, Tuy An district. In which, there are 2 ground problems related to the issue of deciding the project progress: weak soil and bridge construction.

Mr. Nguyen Van Thang requested Phu Yen province to quickly and completely handle the site clearance, ensuring maximum benefits for the people.

“Although the amount of land that has not yet been cleared is not much, I suggest that Phu Yen province focus on completely resolving this issue. During the implementation process, when we have applied all the beneficial things, but if there are cases of deliberate delay and refusal to hand over, we definitely request the province to organize enforcement and make decisions. List this. We are very clear, the rights must be guaranteed to the maximum for the people. In the remaining cases of procrastination, we must handle them drastically, otherwise it will affect the circulation of the entire route," Mr. Nguyen said. Van Thang said.





Nguon

Same topic

'Terrible' congestion on Thang Long Avenue because construction fences have not yet been adjusted

March 20, 03 | 2024:17 TPO - The representative of the Hanoi Traffic Police Department requested to adjust and use soft - mobile fences, but this morning and noon (March 43) Thang Long Avenue section passing the Le Quang Dao street project was extended. still clogged...

Dak Nong attracts investment on three pillars: industry, agriculture and tourism

Dak Nong attracts investment on three pillars: industry, agriculture and tourism. Dak Nong province has attracted 3 investment projects with a total investment capital of about 476 billion VND; will focus on attracting investment on three pillars: industry, agriculture and tourism. Mr. Duong Minh Chau, Deputy Director of Department...

The shape of the longest overpass on the North-South Expressway after Hop Long

Nghe AN-Hung Duc Bridge spanning the Lam River, connecting Nghe An and Ha Tinh, is the longest river crossing bridge on the North-South Expressway, expected to be completed in early May. Duc Hung - Do Nam Vnexpress.net Source

JICA supports upgrading the Northern Nghe An irrigation system

The inauguration ceremony of the project "Restoring and upgrading the Northern Nghe An irrigation system" took place recently at the focal project, Do Luong district, Nghe An province. 2. Delegates took souvenir photos at the Bac Nghe An irrigation system project. Attending the ceremony was Mr. Nguyen Hoang Hiep...

The project to raise the clearance of bridges in the Mekong Delta encountered difficulties because of land problems

On March 23, Deputy Minister of Transport Nguyen Xuan Sang and his delegation...

Highlights

New Posts

Same author

VNDirect "falls" - It's a matter of ensuring information security

VNDirect "falls" - It is vital to ensure information security. Compared to the attack that occurred at a securities company nearly 3 years ago, the attack incident that occurred at VNDirect was more serious when the entire attack stopped. system and service recovery times are longer. VNDirect's anti-attack fence...

Commencement of a railway renovation project worth more than VND 2.000 billion in Quang Binh

Commencement of a railway improvement project worth more than 2.000 billion VND in Quang Binh On the morning of March 22, in Tuyen Hoa district, Quang Binh province, a ceremony to launch the construction of the railway improvement project in the Khe Net pass area, belonging to Quang Binh province, took place. Hanoi - City railway. Ho Chi Minh. Attending the ceremony were leaders of the Ministry of Transport; leader...

VN-Index dropped nearly 14 points in the first session of the week, NVL traded suddenly

VN-Index dropped nearly 14 points in the first session of the week, NVL traded suddenly. The stock market fluctuated negatively in the first session of the week when the majority of stock industry groups went down, while many real estate stocks went against the trend. general direction. VN-Index at the weekend reached its highest level of the session at 1.291,27, but could not hold,...

Much read

Arrange three branches into three new companies in 2024

Biwase General Meeting of Shareholders: Arrange three branches into three new companies in 2024 On the morning of March 25, Joint Stock Company - Binh Duong Water - Environment Corporation (Biwase, code BWE - HoSE floor) held the Annual General Meeting of Shareholders 3. In addition to the Report of the Board of Directors and the General Director on business results in the year...

Proposal to adjust the minimum wage to increase by 6% from July 1, 7

Proposal to adjust the minimum wage to increase by 6% from July 1, 7. The Ministry of Labor, War Invalids and Social Affairs is drafting a Decree regulating the minimum wage for employees working under labor contracts. Accordingly, the Ministry proposes to adjust the minimum wage by 2024% compared to the current level to apply from July 6, 1. ...

VN-Index is potentially shaking before reaching 1.300 points

VN-Index fluctuated rapidly; The market moves towards 1.300 points; PNJ maintains positive revenue; Vincom Retail leaves Vingroup, welcomes back "female general"; dividend payment schedule... ...

Same category

VNDirect "falls" - It's a matter of ensuring information security

VNDirect "falls" - It is vital to ensure information security. Compared to the attack that occurred at a securities company nearly 3 years ago, the attack incident that occurred at VNDirect was more serious when the entire attack stopped. system and service recovery times are longer. VNDirect's anti-attack fence...

Increase North-South passenger trains

Specifically, train SE11 departs Hanoi station at 21:20 p.m. and arrives at Saigon station at 11:20 a.m. In the opposite direction, train SE12 departs Saigon station at 19:25 p.m. and arrives at Hanoi station at 9:20 a.m. One-way round-trip ticket price with seats starts from 958.000 VND/ticket; Bed from 1.170.000 VND/ticket or more, depending on travel date and seat type. In addition, to meet the needs of passengers, the railway industry also runs additional trains SE30/SE29 between...

Commencement of a railway renovation project worth more than VND 2.000 billion in Quang Binh

Commencement of a railway improvement project worth more than 2.000 billion VND in Quang Binh On the morning of March 22, in Tuyen Hoa district, Quang Binh province, a ceremony to launch the construction of the railway improvement project in the Khe Net pass area, belonging to Quang Binh province, took place. Hanoi - City railway. Ho Chi Minh. Attending the ceremony were leaders of the Ministry of Transport; leader...

VN-Index dropped nearly 14 points in the first session of the week, NVL traded suddenly

VN-Index dropped nearly 14 points in the first session of the week, NVL traded suddenly. The stock market fluctuated negatively in the first session of the week when the majority of stock industry groups went down, while many real estate stocks went against the trend. general direction. VN-Index at the weekend reached its highest level of the session at 1.291,27, but could not hold,...

New Posts

Cancelo: 'Guardiola lies, Man City is ungrateful'

Portuguese defender Joao Cancelo criticized coach Pep Guardiola and Man City in the incident that caused him to leave the English team in January 1. Coach Guardiola and Cancelo in a match between Man City and Liverpool in the Premier League. Photo: DPA The Portuguese defender was angry when Guardiola told the media that...

The float caught fire while parading on Da Nang street

On the evening of March 25, a flower cart decorated with propaganda and promotion for the 3 Avalokiteshvara Festival (Ngu Hanh Son, Da Nang city) caught fire while parading on Phan Chau Trinh street (Hai Chau district).When When a fire broke out, the authorities quickly used a fire extinguisher to put out the fire so no...

Tien Giang improves the quality of Party activities according to Regulation 213

Shortcomings and limitations that need to be overcome During a recent 213 party member activity at My Hung hamlet cell, My Phong commune (My Tho city), an elderly party member complained: "It's past meeting time and just There were several party members in attendance. Comrades who are absent do not respect the organization....

New Posts

Taj Mahal at dawn