Prime Minister Pham Minh Chinh has just signed Official Dispatch No. 517/CD-TTg dated June 6, 6 on the implementation of solutions to ensure electricity supply in the dry season in 2023 and in the future.
Public telegram to the Minister of Industry and Trade; Chairman of the Committee for Management of State Capital at Enterprises; Presidents of People's Committees of provinces and centrally run cities; Chairman, general director of corporations: Electricity of Vietnam, Vietnam Oil and Gas, Vietnam Coal - Mineral Industry, stated:
The hot and hot situation and the impact of the El Nino phenomenon in many places throughout the country have increased the demand for electricity and daily life of the people, combined with the shortage of rain in the Northern provinces, so the water to the hydroelectric lakes is very low, which has greatly affected the supply of electricity in the dry season in 2023. The Prime Minister has directed in many early forms, from the dry season of the year of the electricity in the dry season, in which the power supply is absolutely not in the dry season, it is absolutely in the year of the electricity supply, in which the power supply is absolutely Specific methods overcome the difficulties in electricity supply over the past time, including notice No. 2023/TB-VPCP dated May 185, 19. Although, Vietnam Electricity Group (EVN), Vietnam Oil and Gas Group (PVN), Coal and Mineral Industry Group (TKV) and relevant agencies and agencies have made an effort to implement some urgent solutions, which have been provided with adequate effects on the time, it has been provided with the factors, but it has been provided to the factors, but it has been provided to the factors, but it has been provided to the factors, but it has been in particular to the fact that it has sufficient effects to the time, it has been provided with the fact that it has sufficient effects in the time, it has been provided with adequate factors, especially the factors, which has been provided with sufficient effects in the time, it has provided the factors in particular. In the North. Facing the current difficult situation of electricity supply, the Prime Minister requested:
1. Ministry of Industry and Trade:
– Review and carefully evaluate the current situation of electricity supply, especially arising factors affecting the assurance of electricity supply to enhance the effectiveness and efficiency of state management, urgently guide EVN to develop proactive scenarios to promptly respond to difficulties in power supply and organize implementation according to regulations. Get this done by June 10, 6.
– Urgently complete the Prime Minister's Directive on enhancing electricity saving in the period of 2023 - 2025 and the following years, under the direction of Deputy Prime Minister Tran Hong Ha, in which focusing on practical and effective solutions in the current difficult period of electricity supply, submit to the Prime Minister for signature and promulgation before June 08, 6.
– Urgently complete the Prime Minister's Directive on ensuring electricity supply, coal and gas supply for electricity production in the near future under the direction of the Prime Minister in Document No. 8230/VPCP-CN dated December 07, 12, and report to the Prime Minister before June 2022, 15.
- Research and guide the final handling according to competence for wind power and solar power projects that have been constructed but fail to meet the deadline for application of the FIT pricing mechanism (which has expired); urgently guide the negotiation of electricity prices in the spirit of "harmonious benefits, shared risks" for wind power and solar power projects mentioned above according to regulations, completed in June 6.
– Review the provisions of the law on electricity to provide guidance on investment in the transmission grid according to the approved electricity development planning, in which to promote investment in the form of public-private partnership in the process of developing and submitting to the Prime Minister for promulgation the Implementation Plan of the Electricity Master Plan VIII.
– Urgently adjust the management and direction of the National Load Dispatch Center to the Ministry of Industry and Trade according to the regulations of the Party and State in June 6 and study and implement appropriate and effective policies.
2. The Committee for Management of State Capital at Enterprises, within its competence and prescribed by law, directs EVN, PVN, and TKV Groups to closely and effectively coordinate in implementing solutions to ensure electricity supply in the dry season in 2023 and the following time; promptly report to the Prime Minister on matters beyond its competence.
3. Vietnam Electricity Corporation:
– Focusing on effectively mobilizing all resources, making the best efforts in directing and administering the synchronous and effective implementation of solutions to ensure electricity supply; strictly comply with regulations and the direction of the Prime Minister and the guidance of the Ministry of Industry and Trade on this issue.
– Actively develop flexible scenarios to cope with difficulties in power supply and follow the guidance of the Ministry of Industry and Trade; at the same time, assume the prime responsibility for, and coordinate with ministries, branches and localities in, organizing the implementation according to regulations.
– Urgently direct and directly troubleshoot power plants, especially power plants in the North to put them into operation as soon as possible.
– Highly focused on effectively implementing solutions to enhance electricity saving, especially in June 6.
4. Coal-Mineral Industry Group, Vietnam Oil and Gas Group supply enough coal and gas for power plants at the request of EVN; closely coordinate with EVN in implementing solutions to ensure electricity supply in the coming time; to urgently direct the troubleshooting of power plants under their authority, which will soon be put into operation in June 6.
5. The People's Committees of the provinces and centrally-run cities shall closely coordinate with EVN, power corporations/companies in carrying out power saving work in the locality with the highest efficiency and implementing scenarios to cope with difficulties in electricity supply in the coming time.
6. Assign the Minister of Industry and Trade to direct the establishment of a specialized inspection team in accordance with the law on electricity supply and management of Vietnam Electricity from January 01, 01 to June 2021, 01.