According to information from the People's Committee of Cua Ong Ward, after the meeting on September 22, 2025, households whose land area was recovered to implement the Quang Ninh LNG Power Plant project agreed and signed to hand over land to implement the project with a total area of nearly 32 hectares.
Specifically, for phase I of the project, the area to be recovered is over 25.4 hectares, affecting 8 households and 2 organizations. Currently, all 8 households have signed the compensation plan and agreed to hand over the site with a total area of 22.88 hectares.
Phase II of the project has an area of 15.7 hectares, affecting 5 households and 4 organizations. Currently, all 5 households have agreed to hand over the land with a total area of 9.1 hectares.
Mr. Nguyen Quoc Hoan, Vice Chairman of Cua Ong Ward People's Committee, said: Along with the area of more than 1.7 hectares that has completed site clearance, Cua Ong Ward People's Committee has completed site clearance of nearly 34 hectares and handed it over to the Investment and Construction Project Management Board of Area II to carry out the next steps of handing over to the project investor. For the area related to organizations, the Ward People's Committee is completing the procedures to recover land in accordance with the schedule directed by the province.
Source: https://baoquangninh.vn/100-ho-dan-dong-thuan-ban-giao-mat-bang-du-an-nha-may-dien-khi-lng-quang-ninh-3377141.html