The construction unit is speeding up the progress of Road No. 3 and the dike along Ca Nhip canal.
In January 2023, Tan Thanh district started construction of Road No. 3 project and exploited land on both sides of the road. The project has a total length of nearly 1km connecting Le Duan Street in Tan Thanh town to National Highway N2, with a 26m wide road surface and asphalt concrete. The construction time is 450 days. This is a very important route connecting Tan Thanh town to National Highway N2 to Ho Chi Minh City and the Western provinces.
The project to upgrade and expand the dike along Ca Nhip canal has a total length of over 8.3km (including 6 bridges) connecting Le Duan Street in Tan Thanh town to Hai Hat canal in Tan Hoa commune and adjacent to Cai Lay town, Tien Giang province, passing through the Dong 41 historical relic stele. This project is divided into 2 sections equivalent to 2 bid packages, construction in 450 days.
Vice Chairman of Tan Thanh District People's Committee - Le Phuoc Ven said that the District People's Committee assigned the District Construction Investment Project Management Board as the investor for the above 2 projects. After the groundbreaking ceremony in January 2023, the contractor quickly implemented the construction of the 2 projects. Up to now, the project of Road No. 3 and the exploitation of land fund on both sides of the road has reached over 45% of the volume. According to the plan, this project will be completed in 2024. In particular, the project to upgrade and expand the dike along Ca Nhip canal has reached 85% of the volume. Currently, the District Construction Investment Project Management Board has strengthened the inspection and supervision of the construction and quality of the project. When these 2 projects are completed, it will facilitate people's travel and trade, contributing to the construction of a new rural district and creating a landscape for the urban area.
According to the Commander of Road No. 3 project (under the contractor Dai A Chau Construction Production Trading Co., Ltd.) - Dinh The Hai, for the Road No. 3 project and the exploitation of land on both sides of the road, up to now, the construction unit has completed the foundation, embankment, and pumped 90% of the construction sand; the longitudinal and transverse culverts are under construction. The unit has focused on a lot of equipment and workers to speed up the progress of the project. It is expected that from now until the end of the year, this project will reach over 75% of the volume.
The project to upgrade and expand the dike along Ca Nhip canal is divided into 2 packages. Dai A Chau Construction Production Trading Co., Ltd. is the contractor for package 1, from Km00 to Km3+00. The package includes the construction of 3 bridges and has been completed. For the road, the contractor has completed 80% of the volume. The unit is currently implementing the asphalt paving from Km1+400 to Km3+00. With this progress, the unit has completed the construction plan by more than 3 months. It is expected that in November 2023, the package constructed by the company will be completed and put into use.
Dai A Chau Construction Production Trading Co., Ltd. is a contractor for civil, industrial, traffic, and technical infrastructure construction projects, specializing in supplying and installing electrical, refrigeration, fire prevention, and fire fighting systems, etc. In Long An , Dai A Chau Construction Production Trading Co., Ltd. is a contractor for many projects that are highly appreciated for their aesthetics, quality, and completion ahead of schedule./.