Nearly 3 trillion VND allocated to key projects.
Dak Nong is currently implementing 84 projects, including both ongoing and new ones. Of these, 6 projects have been identified as key projects.
Specifically, the projects include: the Dao Nghia - Quang Khe Road Project Phase 2; the Dak Nong Provincial General Hospital Upgrade Project; the Gia Nghia City Central Square Project; the relocation and resettlement project for 212 households in the central area of Gia Nghia City; the Gia Nghia Lake Project; and the Dak Nong Provincial Museum, Library and Park Complex Project.

The total investment capital for the six key projects is 2,982 billion VND. These key projects belong to various fields.
The second phase of the Dao Nghia - Quang Khe Road project has a total investment of 830 billion VND. This project connects National Highway 14 with National Highway 28, facilitating traffic flow into Lam Dong province. The project has a total length of 47.4 km.

Upon completion, the project will meet transportation needs and boost the flow of goods and services for the people. It will also be a key transportation route to serve the development of the bauxite and aluminum electrolysis industries.

The Dak Nong Provincial General Hospital Upgrade Project was approved by the Provincial People's Committee in Decision 2281/QD-UBND, dated December 22, 2021. The total investment for the project is 753 billion VND.
The completed facility, once put into operation, will meet the healthcare needs of the people in the province. The project will also create a better working environment for doctors and medical staff, allowing them to develop their expertise and skills.

The Gia Nghia City Central Square project officially commenced on December 27, 2022. The total investment for the project is 400 billion VND. This is a project of particularly significant importance. Upon completion, the project will create a highlight in terms of architectural space and urban landscape for Gia Nghia City in particular and Dak Nong province in general.

Initially, some completed sections of the project will serve as the venue for Dak Nong to host the 20th anniversary celebration of the re-establishment of Dak Nong province, scheduled to take place in March 2024.
Playing a strategic role
According to Mr. Nguyen Van Nghia, Director of the Dak Nong Provincial Investment and Construction Project Management Board (Project Management Board), the Provincial Party Committee, the Provincial People's Council, and the Provincial People's Committee pay special attention to and direct the implementation of key projects.

Each key project demonstrates political determination and the consensus of the government and the people. "Although the projects are implemented under extremely difficult conditions, they always receive close attention and guidance from the province," Mr. Nghia said.
According to Ho Van Muoi, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, the disbursement of public investment capital in general, and key projects in particular, is of great significance to Dak Nong.
Each project completed on schedule will help Dak Nong promote its economic and social development. The province's appearance will also be significantly improved and modernized.

"All levels and sectors, from the grassroots, must get involved decisively to share responsibility with the province. People in the project areas need to support and agree with the province's policies to work together towards common goals," Chairman of the Provincial People's Committee Ho Van Muoi expressed.