Vietnam.vn - Nền tảng quảng bá Việt Nam

Speeding up the progress of projects in Mai Son Industrial Park

On July 15, at Mai Son Industrial Park, Mr. Nguyen Thanh Cong, Vice Chairman of the Provincial People's Committee and the provincial delegation worked with leaders of departments, branches, the Provincial Industrial Park Management Board and Chieng Mung commune on the progress of project implementation in Mai Son Industrial Park; progress of site clearance compensation and investment in common infrastructure in the Industrial Park.

Báo Sơn LaBáo Sơn La15/07/2025

The Vice Chairman of the Provincial People's Committee worked on the progress of project implementation in Mai Son Industrial Park.

Mai Son Industrial Park has a scale of 150 hectares, and is implementing phase I with an area of 63.7 hectares. Technical infrastructure items such as water supply system, wastewater treatment, internal traffic roads... have reached 85 - 92% of the volume. Some items have been basically completed and are being tested for operation. The water supply system with a capacity of 5,000 m³/day and night has reached 88% of the volume; the wastewater treatment system with a capacity of 2,500 m³/day and night is completing the incident reservoir to put into synchronous operation. The 4.2 km long traffic route has completed 3.6 km of construction.

Delegates attending the meeting.

The Industrial Park Management Board has also completed the adjustment of design documents and invested in an environmental incident prevention system - a necessary condition for obtaining an Environmental License. The items of electricity supply, clean water, and infrastructure operation are being accelerated, expected to be submitted to competent authorities for approval in July 2025.

Provincial Industrial Parks Management Board reports on implementation progress.

For the Instant Cereal and Dried Fruit Factory Project of VFI Investment Trading Production Joint Stock Company, about 80% of the volume has been completed, equipment is being installed, and a trial run is expected from September 15, 2025. The BHL Son La Modified Starch Processing Factory Project has completed the main structure, auxiliary systems are being urgently completed, and is expected to be inaugurated at the end of September. The Mavin Mai Son Animal Feed and Agricultural Products Processing Factory Complex Project is completing land allocation procedures, preparing to start construction in August 2025.

Representative of BHL Agricultural Products Processing Joint Stock Company reported the progress of BHL Son La modified starch processing factory project.

The site clearance work of nearly 18 hectares has been stuck since 2008 due to the lack of resettlement land. In addition, the progress of pricing water supply, infrastructure services, and environmental licenses is slow, and the road leading to the industrial park has deteriorated.

The Vice Chairman of the Provincial People's Committee spoke at the meeting.

The Vice Chairman of the Provincial People's Committee requested the Provincial Industrial Park Management Board to coordinate with the People's Committee of Chieng Mung commune to unify the establishment of a Compensation Council for Land Acquisition and Site Clearance, focusing on propaganda, mobilization, and persuasion to create consensus among the people in the Land Acquisition and Site Clearance. Departments and branches urgently complete the remaining documents and procedures, such as: Environmental licenses, service pricing, electricity system investment, etc. Investors of secondary projects need to focus resources, ensure quality, construction progress, and strive to put the factory into operation as committed.

The comrade assigned the Management Board of Industrial Parks to proactively work with relevant parties, promptly remove difficulties, commit to completing the power supply for new factories before July 30 and agree to propose to the Northern Electricity Corporation to build a 110kV station for the Industrial Park. The Department of Agriculture and Environment completed the issuance of Environmental License before August 10; completed land procedures so that the Mavin Animal Feed and Agricultural Products Processing Complex Project could start construction on August 19... The goal is that by September 2025, Mai Son Industrial Park will have 2 more factories in operation, one project starting construction and basic technical infrastructure completed, qualified to attract the next investors.

Source: https://baosonla.vn/thoi-su-chinh-tri/day-nhanh-tien-do-cac-du-an-trong-khu-cong-nghiep-mai-son-mYrt5DUNR.html


Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product