On June 28, Senior Lieutenant General Trinh Van Quyet, member of the Party Central Committee, member of the Central Military Commission, Director of the General Department of Politics of the Vietnam People's Army, chaired an inspection of the progress of the workload of the Vietnam Military History Museum project.
With a much larger volume of work to be done compared to the inspection on May 9, there has been a change at the construction site of the Vietnam Military History Museum, and so far the progress has basically been completed according to the conclusion of the Director of the General Department of Politics.
The investment project to build the Vietnam Military History Museum has been identified by the Central Military Commission and the Ministry of National Defense as one of the current key projects; the Project Management Board has made great efforts to carry out a large volume of construction and display work, basically meeting the requirements; ensuring quality and safety; management work is strictly ensured, in accordance with the provisions of law.
According to the reports of the units, by July 30, the construction packages outside the house will be completed to test the connection of the systems; by August 30, 2024, the entire workload of the main building will be basically completed, the outdoor and indoor displays will be completed; from September 1, the connection of all construction systems in phase 1 will be organized and handed over for use in October.
Senior Lieutenant General Trinh Van Quyet acknowledged the efforts in organizing and implementing the project of the competent authorities, contractors, and the coordination and guidance of the competent authorities of the Ministry of National Defense for the investor to implement the project smoothly and in accordance with the law.
Senior Lieutenant General Trinh Van Quyet requested the Project Management Board and the agencies of the General Department of Politics to organize the implementation in accordance with the regulations of the State and the Ministry of National Defense on construction investment management; organize construction to ensure safety, aesthetic requirements and quality according to approved design documents; promote the sense of responsibility and business reputation, seize the time, drastically increase human resources, organize management, scientific construction, speed up progress in the bidding package works.
Members of the Project Management Board, according to their assigned duties and responsibilities, continue to promote their sense of responsibility, proactively coordinate more closely with the standing agency to implement the project to ensure technical, quality, progress and absolute safety.
The competent agencies of the Ministry of National Defense continue to pay attention, create favorable conditions to help and guide the Investor and the Project Management Board on legal procedures throughout the project implementation process, comply with legal regulations, promptly report to the Ministry of National Defense on difficulties, problems, recommendations and proposals of the Investor so that the project can be implemented most smoothly, completed before the 80th anniversary of the founding of the Vietnam People's Army, the 35th National Defense Festival and the 80th anniversary of the General Department of Politics of the Vietnam People's Army./.
Source: https://www.vietnamplus.vn/day-nhanh-tien-do-xay-dung-du-an-bao-tang-lich-su-quan-su-viet-nam-post961888.vnp