Van Mieu Park in Vo Cuong ward is constructed by the joint venture of Bac Ninh Trade and Service Joint Stock Company and Duy Linh Construction and Renovation Limited Liability Company.
After more than 5 months of implementation, the construction progress has reached more than 90% of the plan. The items have been completed such as: 2 auxiliary houses; fountain pool; water supply and drainage system; garden lighting; landscape hill... Currently, the contractor is mobilizing 35 engineers and workers to complete the final item, which is the stone yard surrounding the 2 auxiliary houses and internal roads.
The contractor is focusing on construction and will soon put the project into operation. |
To ensure progress, the contractor divided the workforce into 3 shifts; gathered all materials at the construction site; spread tarpaulins to protect the construction area when it rained... According to the construction site management department, relevant units regularly held meetings to promptly resolve arising problems. The work of quality management, technical aesthetics, labor safety, and construction site sanitation was focused on and implemented effectively.
Construction of two auxiliary buildings was completed in early July. |
The project of infrastructure and auxiliary works of Van Mieu Park (phase 1) has a total investment of nearly 700 billion VND from the provincial budget. On an area of 5 hectares, the project includes items such as: Uncle Ho Temple, Square, landscape hill, lotus pond, auxiliary works and modern technical infrastructure system.
Along with striving to complete phase 1, the investor is preparing to implement the next phase of the project. It is expected that when completed, the project will become an important cultural and tourist highlight of the province.