The resettlement area construction investment project serving the Lao Cai- Hanoi -Hai Phong railway construction investment project is being implemented in the following locations: Duong Kinh ward, An Khanh commune, An Hung commune, Kien Thuy commune and Kien Hai commune. In particular, the resettlement area in Duong Kinh ward has an area of 74,853.9 m², with a total investment of 283.9 billion VND, and is expected to start construction on August 19.

The Ring Road 2 project, Tan Vu - Hung Dao - Bui Vien Street section, started construction in early March 2025. However, due to problems in site clearance, the progress of construction packages has not met requirements. Specifically: Package 19 (construction of Tan Vu intersection and the section to the beginning of Lien Phuong Street intersection) reached 5% of the plan; Package 20 (from Lien Phuong Street intersection to the end of Hai Thanh overpass intersection) reached 19.1%; Package 21 (from the end of Hai Thanh overpass intersection to the beginning of Bui Vien Street overpass intersection) was just handed over the site on July 20; Package 22 (construction of Bui Vien Street intersection) reached 11%; Package 23 (construction of technical infrastructure for resettlement areas) has completed selecting contractors. Currently, construction units are mobilizing machinery and human resources to receive the site and start construction.

To ensure disbursement and construction progress, at the meeting, the Hai Phong Traffic and Agricultural Construction Investment Project Management Board requested the People's Committees of Hai An, Hung Dao, Kien An wards and the Regional Project Management Board to urgently speed up site clearance work, creating favorable conditions for contractors to carry out construction.
Representatives of local authorities and the Project Management Board of Hai An, Duong Kinh, and Kien An areas affirmed that they will take drastic action and committed to handing over the site in September.

After checking and listening to the reports of leaders of units and localities at the meeting, Standing Vice Chairman of the City People's Committee Le Anh Quan acknowledged the efforts of Duong Kinh ward, the Project Management Board of Hai Phong traffic and agricultural works, and the Project Management Board of Duong Kinh area in accelerating the progress of site clearance, ready to start the resettlement area serving the Lao Cai - Hanoi - Hai Phong railway project on August 19, 2025, this is one of the 3 key projects of the city among the total of 80 projects and key works organized to start construction and inaugurate at 80 online bridges across the country to celebrate the August Revolution and National Day September 2. Therefore, the Standing Vice Chairman requested the units to urgently complete the work of organization, propaganda, and mobilization of people's consensus, handing over the site on schedule.
Regarding the Ring Road 2 Project (Tan Vu - Hung Dao - Bui Vien section), the Standing Vice Chairman emphasized that this is a key project in 2025, with priority given to large capital but the progress has not met the requirements due to problems with site clearance. The Standing Vice Chairman assigned Hai An ward to urgently pay all compensation, ensure security and order, and strive to complete in August 2025; Kien An ward to coordinate in inventory, approve compensation plans, and develop enforcement plans for cases of intentional non-handover; Hung Dao ward and the Duong Kinh area Project Management Board to build a critical road with detailed construction progress, complete site clearance as required, review documents, arrange resettlement, consider temporary shelter support for households, and coordinate with departments and branches to handle petitions on land allocation with payment.
The Standing Vice Chairman highly appreciated the efforts of the Project Management Board, requested to urgently determine the land needs for each bid package, urge contractors to accept and construct, and mobilize maximum equipment and human resources./.
Source: https://thanhphohaiphong.gov.vn/khan-truong-ban-giao-mat-bang-bao-dam-tien-do-02-du-an-giao-thong-trong-diem.html