Dong Thap provincial leaders survey key traffic projects

DTO - On July 24, Chairman of Dong Thap Provincial People's Committee Tran Tri Quang and leaders of specialized departments and branches conducted a field survey and inspected the construction progress of a number of key traffic projects in the province.

Báo Đồng ThápBáo Đồng Tháp24/07/2025


Chairman of the Provincial People's Committee Tran Tri Quang (4th from left) surveys the project to build route DT.857 from National Highway 30 to DT.845.

In An Long Commune (formerly An Phong Commune), the working group inspected the construction progress of the An Phong - Tan Binh Ferry Terminal Project. This is a traffic project that plays an important role in inter-regional connectivity, serving the travel and freight transport needs of people on both sides of the Tien River. Currently, the main items of the project have been basically completed and are expected to be put into operation in August 2025.

During the survey, Chairman of the Provincial People's Committee Tran Tri Quang requested the Provincial Project Management Board to urgently complete the remaining items, especially the infrastructure on both sides of the wharf. At the same time, the investor needs to closely coordinate with relevant departments and branches to speed up the acceptance and licensing procedures and complete the preparation for operation. Chairman of the Provincial People's Committee Tran Tri Quang emphasized: "Putting An Phong - Tan Binh Ferry Terminal into operation on schedule in August will create favorable conditions for socio -economic development, connecting remote areas with administrative centers and key traffic routes".

Next, the Working Group surveyed the construction progress of the DT.857 Road Construction Project from National Highway 30 to DT.845. The route is about 45 km long, started in July 2022, with a scale of a level IV plain road, a 9m wide roadbed, and a 7m wide asphalt road surface. There are a total of 27 bridges and 58 cross-road culverts (including 12 box culverts) on the route, divided into 10 construction packages.

According to the report of the Department of Construction, the total capital allocated for the project is VND 1,600.782 billion/VND 2,179.79 billion. The cumulative payment value of construction packages up to now is VND 540.345 billion/VND 1,121.064 billion, equivalent to 48.24%. From June 2025, the project will be supplemented with sand, creating favorable conditions to accelerate progress. Currently, the bridge section on the route has basically completed over 90%; the road section is being urgently implemented, expected to be completed in 2025.

However, the project still faces some difficulties, especially problems in site clearance and shortage of raw materials such as sand and construction stone. These are factors that directly affect the progress and quality of the project.

Chairman of the Provincial People's Committee Tran Tri Quang highly appreciated the efforts of the investor, contractors and local authorities in implementing the project, and shared the difficulties that the construction unit encountered, especially the shortage of construction materials, and said that the province will actively coordinate with relevant departments to support and remove obstacles in the supply of materials. Chairman of the Provincial People's Committee Tran Tri Quang also requested the project management unit and supervision consultant to regularly inspect the site and urge the construction contractor to ensure the progress, quality and safety of the project.


Chairman of the Provincial People's Committee Tran Tri Quang came to survey the project to upgrade and expand National Highway 30, Cao Lanh - Hong Ngu section (phase 3)

On the same day, Chairman of the Provincial People's Committee Tran Tri Quang inspected the Project to upgrade and expand National Highway 30, Cao Lanh - Hong Ngu section (phase 3). This project has a total investment of 793.19 billion VND. To date, the implementation value has reached 662.5 billion VND, equivalent to 83.5%. The investor is focusing on constructing the final items, striving to complete and organize technical traffic opening by the end of September 2025.


Contractors are speeding up the implementation of items to ensure the project to upgrade and expand National Highway 30, Cao Lanh - Hong Ngu section (phase 3)
is technically open to traffic by the end of the third quarter of 2025.

Chairman of the Provincial People's Committee Tran Tri Quang emphasized the importance of traffic works for the socio-economic development of the province, and at the same time requested relevant units to continue to promote a sense of responsibility, speed up progress, ensure quality, and soon put the works into operation to serve the people.

My Ly

Source: https://baodongthap.vn/kinh-te/lanh-dao-tinh-dong-thap-khao-sat-cac-cong-trinh-giao-thong-trong-diem-133132.aspx


Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product