(Baoquangngai.vn) - Chairman of the Provincial People's Committee Nguyen Hoang Giang noted that investors must increase their responsibility, coordinate to resolve difficulties, and be determined to speed up construction and disbursement progress, striving to disburse 80% of the province's public investment capital plan by the end of 2024.
On the afternoon of November 16, Chairman of the Provincial People's Committee Nguyen Hoang Giang chaired a meeting to evaluate the results of public investment disbursement in the first 10 months of 2024; the implementation of key projects; key tasks and works in public investment in the last 2 months of 2024. Vice Chairman of the Provincial People's Committee Tran Phuoc Hien; directors of departments, branches; leaders of People's Committees of districts, cities and towns in the province attended.
Director of the Provincial Traffic Construction Investment Project Management Board Ngo Van Dung presented solutions for disbursing public investment capital in the last months of 2024 at the meeting. |
Speaking at the opening of the meeting, Chairman of the Provincial People's Committee Nguyen Hoang Giang highlighted the significance and importance of accelerating the disbursement of public investment capital for local economic and social development. At the same time, emphasizing that there are only 45 days left until the end of 2024, the province requested that agencies advising the Provincial People's Committee on disbursement work must classify this work into 3 groups, including the group exceeding, the average group and the group below the general disbursement rate of the whole country to have appropriate solutions to promote disbursement. "The province assigned Vice Chairman of the Provincial People's Committee Tran Phuoc Hien to work with the group of low-disbursement investors to urge; direct financial agencies and treasuries to establish payment procedures and disburse capital promptly when there is a quantity" - Chairman of the Provincial People's Committee Nguyen Hoang Giang emphasized.
Representatives of the People's Committee of Quang Ngai City reported on the disbursement of public investment capital in 2024 at the meeting. |
According to the report of the Department of Planning and Investment at the meeting, the total public investment capital plan for 2024 of the province is more than 6,900 billion VND; as of October 31, only about 1,940 billion VND has been disbursed, equal to 28.1% of the assigned capital plan. Of which, local budget capital disbursed 1,496 billion VND, equal to 29.7% of the assigned capital plan; Central budget capital disbursed 444 billion VND, equal to 23.9% of the assigned capital plan. Particularly for 8 key projects of the province, the disbursement rate as of October 31 was only over 21%. Up to now, Quang Ngai still has 3,700 billion VND undisbursed, in which the investor with the largest undisbursed capital is the Provincial Traffic Construction Investment Project Management Board (1,617 billion VND undisbursed). Notably, in 2024, Quang Ngai has 49 projects transferred from 2023, of which 33 projects must be completed in 2024, but currently the disbursement rate of many projects is still very low.
Vice Chairman of the Provincial People's Committee Tran Phuoc Hien spoke at the meeting. |
Currently, the whole province has only 7 investors disbursing higher than the national average (Tu Nghia, Duc Pho Town, Nghia Hanh, Ba To...); 9 investors disburse at the average level (Dung Quat Economic Zone Management Board and provincial industrial parks; Management Board of investment projects for construction of civil and industrial works; Son Ha, Minh Long, Ly Son, Son Tay districts...); and 10 investors disburse lower than the national average rate (Quang Ngai City, Binh Son, Tra Bong districts...).
At the meeting, project investors with low disbursement rates reported the reasons for slow disbursement and made a commitment to speed up the disbursement progress in the remaining months of 2024. Accordingly, the reasons for slow disbursement are due to problems with foreign capital procedures; slow capital arrangement; slow bidding and contractor selection; problems with site clearance, no district-level land use planning, etc. Investors in this group committed to bringing the disbursement rate to 50% - 99% of the assigned capital plan by December 31, 2024. According to estimates by the Department of Planning and Investment, the disbursement rate of the whole province by the end of November 2024 will reach about 40%; by the end of 2024, it will reach about 80%.
Chairman of the Provincial People's Committee Nguyen Hoang Giang delivered a concluding speech at the meeting. |
Concluding the meeting, Chairman of the Provincial People's Committee Nguyen Hoang Giang requested investors with low disbursement rates to discuss solutions to speed up construction progress and capital disbursement. In particular, the Provincial Traffic Construction Investment Project Management Board, which is the investor of 8 key projects in the province; the Management Board of Dung Quat Economic Zone and the provincial industrial parks, must have a weekly plan to remove obstacles and increase the disbursement rate higher than the committed level.
Chairman of the Provincial People's Committee Nguyen Hoang Giang noted that investors must closely follow the construction site, take advantage of favorable weather, urge contractors to mobilize human resources and machinery to work overtime, and compensate for previously delayed volumes. The Department of Natural Resources and Environment must actively support localities to remove obstacles, guide the issuance of land prices, and serve as a basis for compensation and site clearance. "The spirit is that all investors must calculate solutions, coordinate well with local authorities to resolve site clearance problems, and be determined to speed up the disbursement progress to achieve the 2024 plan," emphasized Chairman of the Provincial People's Committee Nguyen Hoang Giang.
News and photos: THANH NHI