Accelerate construction of key transportation projects.

These days, the Ring Road 2 and Nguyen Trai Bridge project is entering a crucial construction phase. The investor and contractors are urgently accelerating the progress of the various components.

Báo Hải PhòngBáo Hải Phòng15/09/2025

ring-2-1
The Ring Road 2 project, specifically the Tan Vu - Hung Dao - Bui Vien section, is one of the city's key projects, with a total investment of 7,020 billion VND. In 2025, the project was allocated 3,218.5 billion VND in funding.
ring-road 2
Due to the low-lying and weak soil, the contractor had to use the soil-cement pile construction method. This method increases stability and reduces settlement of the soil foundation.
rim-2-4
The section from the inter-ward road intersection to the end of the Hai Thanh overpass intersection has completed 331/520 bored piles and 15/42 abutments.
ring-2
The workers are working diligently on the construction site, ensuring that the project is completed on schedule.
ring-2
Land clearance work is being prioritized and expedited by the localities where the projects pass through. In the photo: Construction of the Ring Road 2 project section through Hung Dao ward.
rim - length 2
At the Bui Vien intersection, 62 out of 98 bored piles, 3 out of 8 pier bases, and 11 out of 88 SPT girder segments have been completed.
ring-2
Despite facing obstacles related to land clearance, the contractors are striving to adhere to the construction schedule.
cau-nguyen-trai 1
The Nguyen Trai Bridge construction and urban renovation project, which commenced in December 2024, is a key transportation project of the city, with a total investment of VND 6,235.5 billion.

cau-nguyen-trai 2
The investor and contractors are providing close supervision.
cau-nguyen-trai 3
The construction site on the Thuy Nguyen ward side is bustling with activity.
cau-nguyen-trai 4
The contractor is determined to carry out the construction of the bridge on the Nguyen Trai road side safely and efficiently.
cau-nguyen-trai 5
To ensure the progress of the projects, the City People's Committee requires localities to complete land clearance by October 2025.
LE DUNG

Source: https://baohaiphong.vn/tang-toc-thi-cong-cac-du-an-giao-thong-trong-diem-520870.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Same author

Heritage

Figure

Enterprise

News

Political System

Destination

Product

Happy Vietnam
Fish

Fish

The happiness of a female soldier

The happiness of a female soldier

I choose INDEPENDENCE

I choose INDEPENDENCE