Speed ​​up construction of key traffic projects

These days, the Ring Road 2 and Nguyen Trai Bridge project is entering an important construction phase. The investor and contractors are urgently speeding up the construction progress of the items.

Báo Hải PhòngBáo Hải Phòng15/09/2025

ring-2-1
The Ring Road 2 project, Tan Vu - Hung Dao - Bui Vien section, is one of the city's key projects, with a total investment of VND 7,020 billion. In 2025, the project was allocated capital of VND 3,218.5 billion.
belt 2
Due to the low and weak ground, the contractor must use the method of constructing soil cement piles. This method increases stability and reduces subsidence of the ground.
ring-2-4
The section from the inter-ward road intersection to the end of the Hai Thanh overpass intersection has completed 331/520 bored piles and 15/42 piers.
belt-2
Workers worked hard on the construction site to ensure the set progress.
belt-2
The site clearance work has been paid attention by the localities where the project passes through, speeding up the progress. In the photo: Construction of the Ring Road 2 project through Hung Dao ward.
ring - length 2
Bui Vien intersection has completed construction of 62/98 bored piles, 3/8 pier bases, and 11/88 SPT girder slabs.
belt-2
Although the project is facing problems related to site clearance, contractors are trying to stick to the construction schedule.
The Left Prince 1
The Nguyen Trai Bridge construction investment project and urban beautification of the surrounding area, which started in December 2024, is a key traffic project of the city, with a total investment of 6,235.5 billion VND.

The Left Prince 2
Investors and contractors focus on close direction.
The Left Prince 3
Construction site on Thuy Nguyen ward side is bustling.
The Left Prince 4
The contractor is determined to carry out the bridge construction on Nguyen Trai Street safely and effectively.
The Left Prince 5
To ensure the construction progress of the projects, the City People's Committee requires localities to complete site clearance by October 2025.
LE DUNG

Source: https://baohaiphong.vn/tang-toc-thi-cong-cac-du-an-giao-thong-trong-diem-520870.html


Comment (0)

No data
No data

Same tag

Same category

This morning, Quy Nhon beach town is 'dreamy' in the mist
Captivating beauty of Sa Pa in 'cloud hunting' season
Each river - a journey
Ho Chi Minh City attracts investment from FDI enterprises in new opportunities

Same author

Heritage

Figure

Enterprise

Dong Van Stone Plateau - a rare 'living geological museum' in the world

News

Political System

Destination

Product