Accelerate construction of key transportation projects.
These days, the Ring Road 2 and Nguyen Trai Bridge project is entering a crucial construction phase. The investor and contractors are urgently accelerating the progress of the various components.
Báo Hải Phòng•15/09/2025
The Ring Road 2 project, specifically the Tan Vu - Hung Dao - Bui Vien section, is one of the city's key projects, with a total investment of 7,020 billion VND. In 2025, the project was allocated 3,218.5 billion VND in funding. Due to the low-lying and weak soil, the contractor had to use the soil-cement pile construction method. This method increases stability and reduces settlement of the soil foundation. The section from the inter-ward road intersection to the end of the Hai Thanh overpass intersection has completed 331/520 bored piles and 15/42 abutments. The workers are working diligently on the construction site, ensuring that the project is completed on schedule. Land clearance work is being prioritized and expedited by the localities where the projects pass through. In the photo: Construction of the Ring Road 2 project section through Hung Dao ward.
At the Bui Vien intersection, 62 out of 98 bored piles, 3 out of 8 pier bases, and 11 out of 88 SPT girder segments have been completed. Despite facing obstacles related to land clearance, the contractors are striving to adhere to the construction schedule. The Nguyen Trai Bridge construction and urban renovation project, which commenced in December 2024, is a key transportation project of the city, with a total investment of VND 6,235.5 billion. The investor and contractors are providing close supervision.
The construction site on the Thuy Nguyen ward side is bustling with activity. The contractor is determined to carry out the construction of the bridge on the Nguyen Trai road side safely and efficiently. To ensure the progress of the projects, the City People's Committee requires localities to complete land clearance by October 2025.LE DUNG
Comment (0)