Day | Time | Area | |
Begin | End | ||
I/ Wards: | |||
1. Phong Dien Ward: | |||
08/29/2025 | 7:30 | 11:00 | Viglacera Infrastructure Development Investment Company - Branch of Viglacera Corporation (Viglacera Wastewater Treatment Plant, Viglacera Clean Water Treatment Plant) |
2. Phong Phu Ward: | |||
08/28/2025 | 7:55 | 10:40 | Dien Huong 3 Shrimp Farm |
13:15 | 15:40 | Dien Mon 1 Shrimp Farming TBA | |
3. Phong Quang Ward: | |||
08/29/2025 | 7:50 | 9:40 | Phong Hai Shrimp Farming 6 |
10:15 | 11:30 | Quang Ngan 1 Station | |
4. Kim Long Ward: | |||
09/03/2025 | 6:00 | 15:30 | - Ly Nam De Street (from house number 234 to Kim Son Pagoda) - (Huong Long Pump Station); |
7:10 | 14:30 | - Nguyen Huu Dat Street (from house number 40 to house number 166); Alley: 6,8, 28, 34, 39, 42, 59, 68, 78, 100, 114, 132, 156, 164, 166 Nguyen Huu Dat; | |
5. Huong An Ward: | |||
08/29/2025 | 7:45 | 15:00 | - Sub-areas Tay An 5, Huong An Settlement, Co Buu T1, Co Buu T2; |
6. Phu Xuan Ward: | |||
8/29/2025 | 7:30 | 16:10 | Thanh Giong Street (from Phan Huy Ich Street to Pham Dinh Ho Street), The Lu (from Thanh Giong Street to Thai Phien Street), Thai Phien (from Tran Nhat Duat to Pham Dinh Ho), Alley 17 Le Trung Dinh (Tay Linh 3 Station) |
08/28/2025 | 7:00 | 14:00 | - Phan The Hiep Business Household, Phan The Ha Business Household; |
7. Thuan An Ward: | |||
08/28/2025 | 7:30 | 14:00 | Hai Tien Residential Area, Hai Binh Residential Area |
8. My Thuong Ward: | |||
09/03/2025 | 8:00 | 16:30 | TDP Trieu Thuy |
9. Vy Da Ward: | |||
08/28/2025 | 7:00 | 11:00 | Ung Binh Street, Nguyen Sinh Cung (from house number 118 to house number 198), Tuy Ly Vuong Street |
7:45 | 8:45 | Tung Thien Vuong Street (from house number 30 to house number 52), Ung Tri Street, Cao Xuan Huy | |
10. Thuy Xuan Ward: | |||
08/28/2025 | 5:15 | 6:15 | Ngo Ha Street (from house number 02 to house number 52), Bui Thi Xuan Street (from house number 554 to house number 566) |
6:30 | 7:30 | Dai Nam Road (from Buddhist Academy to An Viet Village), Dong Cat National Urban Area. | |
11. Thanh Thuy Ward: | |||
08/29/2025 | 6:30 | 17:30 | Part of Thanh Thuy Ward: |
12. Huong Thuy Ward: | |||
08/28/2025 | 7:30 | 17:30 | Tan To Substation: Tan To Village, Chiet Bi Village; Tan To Substation 3: Tan To Village, Ton Da 1 Village, Chiet Bi Village |
13. Phu Bai Ward: | |||
09/02/2025 | 7:30 | 17:30 | Viet Phat Plastic Packaging Company Limited (Viet Phat Plastic Packaging Company, Thai Hoa Company) |
09/03/2025 | 8:00 | 10:30 | Phuoc Thanh Electrical Equipment Joint Stock Company (Phuoc Thanh Electrical Equipment Sub-Company); |
II/ Communes: | |||
1. Quang Dien Commune: | |||
08/28/2025 | 7:00 | 15:00 | Niem Pho Village (Niem Pho Substation; Dong Vinh Agricultural Production and Service Cooperative, Quang Tho 1 Agricultural Cooperative (Dong Lam Pump and Drainage Substation) |
8:20 | 13:00 | - The villages of Khuon Pho, Thu Le, Phuoc Thanh, Phu Luong B, Niem Pho; | |
8:30 | 16:15 | Agricultural Production, Business and Service Cooperative No. 1, Sia Town (TBA Pump Kenh Tro) | |
9:50 | 15:00 | Thu Le village, Khuon Pho village (Branch A of Dong Phuoc substation) | |
2. Binh Dien Commune: | |||
08/28/2025 | 7:30 | 16:30 | Substations Hong Tien 1, Hong Tien 2, Hong Tien 3 |
3. Vinh Loc Commune: | |||
08/28/2025 | 7:30 | 12:30 | - Vinh Hien Commune People's Committee Substations; Vinh Hien Substations 3, 4, 5; |
08/29/2025 | 6:30 | 15:30 | Vinh My Commune (old) |
4. Chan May Commune - Lang Co: | |||
08/29/2025 | 7:30 | 12:00 | Bao Nguyen Chan May 68 Trading & Service Company Limited (TBA Bao Nguyen 68) |
5. Nam Dong Commune: | |||
09/03/2025 | 7:30 | 14:30 | La Van Village, A Xach Village |
6. A Luoi Commune 5: | |||
08/28/2025 | 7:30 | 16:30 | Lay off 75% of the capacity of the Song Bo solar power cluster (Xuan Son Clean Energy and Agriculture Company Limited - TBA NLSXS Solar; Trieu Dai Energy Investment Company Limited - TBA NLTD Solar); D4 Vietnam Investment Company Limited - TBA D4VN Solar); Vinh Hai Energy Development Company Limited - TBA NLVH Solar; Agricultural and Clean Energy Development Company Limited - TBA NLS Solar, TBA NLSAL Solar). |
Source: https://huengaynay.vn/kinh-te/thong-bao-lich-tam-ngung-cung-cap-dien-tren-dia-ban-thanh-pho-hue-tu-ngay-28-8-2025-den-ngay-3-9-2025-156958.html