On November 26, the Provincial Traffic Construction Investment Project Management Board and the Project Investor Consortium held the opening ceremony of Tunnel No. 2, right tube in Ban Neng hamlet, Thuy Hung commune (Thach An).
Tunnel No. 2 is one of the important bottlenecks of the Dong Dang (Lang Son) - Tra Linh ( Cao Bang ) Expressway Project under the form of public-private partnership (PPP). With the spirit of "Crossing rivers to build bridges, crossing mountains to dig mountains, crossing fields to pour soil and sand", "building the straightest, shortest and fastest route possible". The tunnel opening ceremony is the result of the efforts, enthusiastic labor, determination of the team of workers, the contractor's engineers, the supervision consultants and the drastic direction to promptly remove difficulties and obstacles of the provincial Party Committee, government and investors.
The right tube of tunnel No. 2, 495 m long, has been dug; the left tube has been dug 348/458 m, about 110 m of tunneling remains to be done and it is expected that the left tube will be dug by mid-December 2024.
The Dong Dang - Tra Linh Expressway project has a total length of 121.06 km, divided into 2 investment phases. Phase 1, invested with a length of more than 93.35 km. The starting point is Km0 + 00 at the Tan Thanh border gate intersection, Van Lang district ( Lang Son ). The end point is at the intersection of Km93 + 350 at National Highway 3, Chi Thao commune, Quang Hoa district (Cao Bang). Phase 2, expands the road section from 2 lanes to 4 complete lanes (with emergency lanes) and builds a new section of 27.71 km connecting Tra Linh and Trung Khanh border gates.
Vu Tiep