Regarding the progress of the bidding packages of Ho Chi Minh City's Ring Road 3 passing through the city, Vice Chairman of the City People's Committee Bui Xuan Cuong requested the Ho Chi Minh City Traffic Construction Investment Project Management Board (Ho Chi Minh City Traffic Board) and contractors to urgently deploy and ensure the correct progress of traffic and technical traffic opening of the bidding packages as required.
Any problems beyond authority (if any) must be promptly reported and the project progress and quality must be taken responsibility according to regulations.
The Ho Chi Minh City Department of Transport urgently establishes a detailed schedule for each construction package, evaluates the feasibility and has the commitment of the construction contractors, and inspects and confirms the consultants to control the established schedule for the entire project to ensure it is according to the set plan. Focus on directing the contractors to complete the Thay Thuoc Canal bridge for technical traffic opening in December 2025, in sync with the Component 7 project of Tay Ninh province.
At the same time, closely coordinate with My Thuan Project Management Board to synchronously carry out the opening of some items of the XL1 package connecting Nhon Trach bridge to the Ho Chi Minh City - Long Thanh - Dau Giay expressway, and report to the Ho Chi Minh City People's Committee before July 20.
The leaders of the Ho Chi Minh City People's Committee requested the project contractors to urgently focus on completing the items and work volume according to the signed contract, ensuring the overall progress according to the set plan; and to be responsible before the law if they violate the contract signed with the investor.
The Department of Construction urgently presides over and coordinates with relevant units to develop a scenario for the opening of the eastern viaduct section and the technical opening of the entire route through the city, ensuring synchronization with the localities through which the project passes.
Including research to add bridge branches of Tan Van intersection to component project 1, add Binh Goi bridge, parallel road and prepare related documents, propose to the city before July 15.
The Binh Duong Traffic Construction Investment Project Management Board was assigned to focus on directing contractors to construct component 5 of the Ho Chi Minh City Ring Road 3 project. In particular, the core part of the expressway through Tan Van intersection must be completed in 2025, ensuring synchronization with the eastern expressway section of component 1, meeting the required progress milestones.
Source: https://ttbc-hcm.gov.vn/tien-do-vanh-dai-3-tp-hcm-xay-dung-kich-ban-thong-xe-doan-phia-dong-1019124.html