Binh Duong accelerates site clearance for key works


(HNM) – In 2023, Binh Duong province simultaneously deploys many key infrastructure projects of provincial and regional scale. The provincial government, localities and related departments, agencies and units are making efforts to speed up site clearance to implement projects on schedule.

Construction of the project of upgrading and expanding National Highway 13 in Binh Duong province. Photo: Quoc Chien

As a key project of Binh Duong province, the National Highway 13 upgrade and expansion project is being aggressively implemented by the construction unit. As noted at the construction site, the construction unit is implementing the clearance sections. However, at present, the power line has not been underground, some sections have not been cleared, which has affected the construction process.

According to Binh Duong Department of Transport, the project of upgrading and expanding National Highway 13 is nearly 13km long, raising it from 6 lanes to 8 lanes. Up to now, the section through Thu Dau Mot city, the province has approved the compensation plan for 23 households and 1 organization, with an amount of more than 103 billion VND; in which, has paid compensation for 20 households and 1 organization, with an amount of nearly 99 billion dong. 16 households and 1 organization have handed over the premises, reaching 71% of the plan.

Chairman of Thuan An City People's Committee Nguyen Thanh Tam said that the National Highway 13 project, the section through Thuan An city, has 464 households and 52 organizations within the scope of clearance. To date, the compensation and support plan has been approved for 293 households and 24 organizations/1.765,9 billion VND (61%); paid compensation and support for 235 households and 8 organizations/1412,2 billion VND (reaching 77%). In which, 92 households and 15 organizations have handed over the premises, reaching 34% compared to the approved households and organizations.

On the local side, Bau Bang district has a key project that is the North Tan Uyen - Phu Giao - Bau Bang power generation route. The route is 48km long, divided into 4 component projects, with a total investment of nearly 3.800 billion VND. Chairman of Bau Bang District People's Committee Vo Thanh Giau said that the project has handed over 99% of the progress. In the coming time, the district proposed the Area Construction Investment Project Management Board to actively coordinate with relevant units to speed up the remaining site clearance for the project to complete as planned.

Another typical key project with regional connectivity that is also being implemented by Binh Duong province is the Ring Road 3 in Ho Chi Minh City (Ring Road 3). The Binh Duong Traffic Construction Investment Project Management Board is proposing to the Provincial People's Committee to direct the People's Committees of Thu Dau Mot, Thuan An and Di An cities to speed up the process of appraisal and approval of compensation, support and resettlement plans, and resolve to disburse capital equivalent to 30% of the site clearance volume before June 30. It is expected that 6% of the entire route will be handed over in June to ensure the start of the project, meet the requirements of completion in 70 and put into operation from 6.

As the locality where the Ring Road 3 project passes, Thu Dau Mot city is expected to complete the disbursement of 6 billion VND in compensation for households this June. Vice Chairman of Thu Dau Mot City People's Committee Vo Chi Thanh informed that the city has 800 affected households with a compensation amount of about 312 billion VND. The city will support people with legal procedures related to land and construction to quickly settle down.

Deputy Director of Binh Duong Traffic Construction Investment Project Management Board, Vo Ngoc Sang, said that the Ring Road 3 project through Binh Duong is more than 26km long. The project has more than 1.500 affected cases, with the recovered land area of ​​nearly 86ha, of which, nearly 1.000 cases are compensated with the amount of about 13.528 billion VND. Up to now, Binh Duong Provincial People's Committee has issued the land unit price for compensation, support and resettlement for the project. On June 2, the Provincial Traffic Construction Investment Project Management Board coordinated with the Land Fund Development Center of Thu Dau Mot City to pay support and compensation. The total amount of compensation and support in Thu Dau Mot city is about 6 billion VND.



Nguon

Same topic

Jogging to respond to the "Earth Hour 2024" campaign

According to the Department of Natural Resources and Environment of Binh Duong province, the running race with the theme "Run for health - Run for the environment" is one of the meaningful activities in the joyful and exciting atmosphere of Youth month, welcoming celebrate the 93rd anniversary of the founding of the Ho Chi Minh Communist Youth Union (March 26, 3 - March 1931, 26) and promote the campaign "All people exercise their bodies following the example of great Uncle Ho" to create...

Giving gifts and receiving support for the poor

At the program, 400 gifts and 0 VND shopping vouchers were given to support people and workers in difficult circumstances in the province. Total program value is over 600...

Give gifts to children and elderly people in difficult circumstances

Also participating in the delegation were representatives of leaders of socio-political organizations, the Department of Labor, War Invalids and Social Affairs of the province. At each destination, the delegation sent warm greetings to...

Businesses relocating from the South to the North enjoy many incentives.

On the afternoon of March 6, a representative of the People's Committee of Binh Duong province said that Chairman of the Provincial People's Committee Vo Van Minh had just chaired a meeting with departments and branches to listen to reports on the implementation of function conversion and relocation. Enterprises located outside the southern industrial zones and clusters enter the northern industrial zones and clusters in the province. Accordingly, the Chairman of Binh Duong Provincial People's Committee requested Departments and branches to participate...

Enhance the role of the Front in the new situation

Ms. Nguyen Thi Hong Van emphasized that the Ward Front needs to continue to effectively implement key tasks such as: Promoting its role and position in consolidating and expanding the bloc...

Highlights

New Posts

Same author

VNPT won the auction for C2 band block for 5G

Vietnam Posts and Telecommunications Group (VNPT) has just won the auction for the C2 band block (3700-3800 MHz) for 5G. On the afternoon of March 19, at the headquarters of the Radio Frequency Department, Ministry of Information and Communications, the National Partnership Auction Company No. 3 held an auction for the rights to use radio frequencies for ice blocks. C5 frequency (2MHz - 3700MHz). Attending the auction, there were Deputy Ministers of...

Vinmec and Techcombank cooperate strategically to optimize customer benefits

Vinmec Health System has just signed a strategic cooperation agreement with Vietnam Technological and Commercial Bank (Techcombank) to optimize benefits for customers and officers and employees of both sides with Tech Wealth health benefits and many other benefits. other benefits. With the motto "Customer is the focus", Techcombank and Vinmec join hands to co-create the best financial and medical solutions to bring essential value...

Agricultural product exports 2024: Expect a breakthrough

In the early days of 2024, Vietnam's agricultural exports recorded strong growth, continuously receiving good news. In January 1 alone, Vietnam's total agricultural export turnover reached 2024 billion USD, an increase of 5,14% over the same period last year. Most groups and industries are growing, expecting a breakthrough this year. Growth in most markets In January 79,2, Vietnam...

Much read

Same category

Learn the process of making Dong vermicelli in So Quoc Oai village

In culinary culture, dong vermicelli is an ingredient used to prepare many attractive dishes and is indispensable in the traditional feasts of the nation. Among the famous vermicelli making villages is So village, a long-standing traditional vermicelli making village in the Northern Delta. Join us to learn about the vermicelli making process here!

Vietnamese cuisine - delicious dishes

Vietnam is a culinary paradise with thousands of delicious dishes from the North - Central - South regions. Every dish has a rich flavor, a harmonious combination of spices and ingredients. From popular eateries to luxury restaurants, all delight visitors. Not only that, Vietnamese dishes are also always warmly welcomed by friends...

The State President attended the Ceremony to receive UNESCO's registration certificate for the art of pottery of the Cham people

On the evening of June 15, UNESCO's Ceremony to register "The Art of Cham Pottery Making on the List of Intangible Cultural Heritage in Need of Urgent Protection" and the opening of the 6 Ninh Thuan Grape - Wine Festival took place. solemnly at April 2023 Square, Phan Rang - Thap Cham city, Ninh Thuan province. ...

Coach Philippe Troussier's teachers and students have a "minimum debut" against Hong Kong (China)

(HNMO) - On the evening of June 15, the Vietnamese team had a minimum 6-1 victory over Hong Kong (China), in an international friendly match at Lach Tray Stadium (Hai Phong). This is also the first official match of coach Philippe Troussier as captain of the national team. ...

Utilities at your fingertips

Helps reduce the administrative work load for teachers, facilitates school management, and helps parents closely monitor their children's learning situation. The preschool connection application belongs to the educational ecosystem. VNPT vnEdu of Vietnam Posts and Telecommunications Group (VNPT) is being evaluated as the top effective solution for preschools in...

New Posts

Build and perfect the law to promote all resources for national development

Regarding the Law on Fire Prevention, Fighting and Rescue (amended), the Government discussed the scope of the Law; the application of international standards and foreign standards to the Law; Fire prevention and fighting solutions and designs for renovated works; responsibility for verification,...

How long does it take for humans to walk around Mars?

If walking along the equator, astronauts need to cross 21.400 km to complete one full circle around Mars and it takes 4.290 hours if traveling continuously. Simulation of an astronaut observing on Mars. Photo: dottedhippo/iStock People have long been interested in Mars and NASA also made plans...

Cancelo: 'Guardiola lies, Man City is ungrateful'

Portuguese defender Joao Cancelo criticized coach Pep Guardiola and Man City in the incident that caused him to leave the English team in January 1. Coach Guardiola and Cancelo in a match between Man City and Liverpool in the Premier League. Photo: DPA The Portuguese defender was angry when Guardiola told the media that...

The float caught fire while parading on Da Nang street

On the evening of March 25, a flower cart decorated with propaganda and promotion for the 3 Avalokiteshvara Festival (Ngu Hanh Son, Da Nang city) caught fire while parading on Phan Chau Trinh street (Hai Chau district).When When a fire broke out, the authorities quickly used a fire extinguisher to put out the fire so no...

New Posts

Taj Mahal at dawn