The bridge under the 280 billion project is under construction at a snail's pace, people are waiting forever for it to open to traffic.

The contractor guaranteed to close and open Tan Binh Bridge to traffic before June 30 as committed, however, halfway through July, the project is still unfinished.

VTC NewsVTC News15/07/2025

In November 2021, the People's Committee of Quang Nam province (old) approved the investment project to build Tan Binh bridge and National Highway 14E bypass through Tan Binh town, Hiep Duc district (now Hiep Duc commune, Da Nang city). The project's goal is to gradually complete the local traffic infrastructure system and relocate and rearrange the population in Tan Binh town, contributing to promoting local socio-economic development.

In November 2021, the People's Committee of Quang Nam province (old) approved the investment project to build Tan Binh bridge and National Highway 14E bypass through Tan Binh town, Hiep Duc district (now Hiep Duc commune, Da Nang city). The project's goal is to gradually complete the local traffic infrastructure system and relocate and rearrange the population in Tan Binh town, contributing to promoting local socio-economic development.

The project has a total investment of 280 billion VND, construction started in April 2022, and is expected to be completed in early 2025.

The project has a total investment of 280 billion VND, construction will start in April 2022 and is expected to be completed in early 2025.

In March 2025, at the inspection of the Tan Binh Bridge project and the National Highway 14E bypass through Tan Binh town, Mr. Le Van Dung - Chairman of the People's Committee of Quang Nam province (old) - requested the contractor to mobilize maximum human resources and machinery and focus on monitoring, urging, and closely checking the construction progress of the project according to the contractor's commitment (including ensuring the closing and technical opening of Tan Binh Bridge before June 30, 2025); in case the contractor does not comply with the commitment, slowing down the project progress, promptly report to the competent authority for consideration and handling.

In March 2025, at the inspection of the Tan Binh Bridge project and the National Highway 14E bypass through Tan Binh town, Mr. Le Van Dung - Chairman of the People's Committee of Quang Nam province (old) - requested the contractor to mobilize maximum human resources and machinery and focus on monitoring, urging, and closely checking the construction progress of the project according to the contractor's commitment (including ensuring the closing and technical opening of Tan Binh Bridge before June 30, 2025); in case the contractor does not comply with the commitment, slowing down the project progress, promptly report to the competent authority for consideration and handling.

However, by mid-July 2025 - past the technical opening date - the bridge under the 280 billion VND project is still unfinished, with local people waiting impatiently.

However, by mid-July 2025 - past the technical opening date - the bridge under the 280 billion VND project is still unfinished, with local people waiting impatiently.

Up to now, the contractor has completed 2 bridge abutments, 7/8 bridge piers; 16/17 horizontal drainage culverts; weathering excavation and clearance of the route corridor of about 3.3/3.41km...

Up to now, the contractor has completed 2 bridge abutments, 7/8 bridge piers; 16/17 horizontal drainage culverts; weathering excavation and clearance of the route corridor of about 3.3/3.41km...

The biggest bottleneck of the project is that the contractor has not been able to construct the T4 pillar of the Tan Binh bridge. This has affected the progress of the closing and technical traffic opening. According to the investor, the T4 pillar has not been constructed due to the frequent heavy rains. The contractor has deployed measures to stop the flow at least twice, but the upstream water level continues to flow back.

The biggest bottleneck of the project is that the contractor has not been able to construct the T4 pillar of the Tan Binh bridge. This has affected the progress of the closing and technical traffic opening. According to the investor, the T4 pillar has not been constructed due to the frequent heavy rains. The contractor has deployed measures to stop the flow at least twice, but the upstream water level continues to flow back.

The contractor is currently focusing on completing the beam installation. However, the fact that the T4 pillar cannot be constructed has affected the progress.

The contractor is currently focusing on completing the beam installation. However, the fact that the T4 pillar cannot be constructed has affected the progress.

In the coming time, the contractor will continue to complete the T4 pillar. Regarding the access road, there is basically enough land to carry out the construction. However, there are still 2 households waiting for resettlement arrangements.

In the coming time, the contractor will continue to complete the T4 pillar. Regarding the access road, there is basically enough land to carry out the construction. However, there are still 2 households waiting for resettlement arrangements.

Thanh Ba

Source: https://vtcnews.vn/cau-thuoc-du-an-280-ty-thi-cong-rua-bo-dan-cho-hoai-chang-thay-thong-xe-ar954529.html


Comment (0)

No data
No data
Magical scene on the 'upside down bowl' tea hill in Phu Tho
3 islands in the Central region are likened to Maldives, attracting tourists in the summer
Watch the sparkling Quy Nhon coastal city of Gia Lai at night
Image of terraced fields in Phu Tho, gently sloping, bright and beautiful like mirrors before the planting season
Z121 Factory is ready for the International Fireworks Final Night
Famous travel magazine praises Son Doong cave as 'the most magnificent on the planet'
Mysterious cave attracts Western tourists, likened to 'Phong Nha cave' in Thanh Hoa
Discover the poetic beauty of Vinh Hy Bay
How is the most expensive tea in Hanoi, priced at over 10 million VND/kg, processed?
Taste of the river region

Heritage

Figure

Business

No videos available

News

Political System

Local

Product