In November 2021, the People's Committee of Quang Nam province (old) approved the investment project to build Tan Binh bridge and National Highway 14E bypass through Tan Binh town, Hiep Duc district (now Hiep Duc commune, Da Nang city). The project's goal is to gradually complete the local traffic infrastructure system and relocate and rearrange the population in Tan Binh town, contributing to promoting local socio-economic development.

The project has a total investment of 280 billion VND, construction will start in April 2022 and is expected to be completed in early 2025.

In March 2025, at the inspection of the Tan Binh Bridge project and the National Highway 14E bypass through Tan Binh town, Mr. Le Van Dung - Chairman of the People's Committee of Quang Nam province (old) - requested the contractor to mobilize maximum human resources and machinery and focus on monitoring, urging, and closely checking the construction progress of the project according to the contractor's commitment (including ensuring the closing and technical opening of Tan Binh Bridge before June 30, 2025); in case the contractor does not comply with the commitment, slowing down the project progress, promptly report to the competent authority for consideration and handling.

However, by mid-July 2025 - past the technical opening date - the bridge under the 280 billion VND project is still unfinished, with local people waiting impatiently.

Up to now, the contractor has completed 2 bridge abutments, 7/8 bridge piers; 16/17 horizontal drainage culverts; weathering excavation and clearance of the route corridor of about 3.3/3.41km...

The biggest bottleneck of the project is that the contractor has not been able to construct the T4 pillar of the Tan Binh bridge. This has affected the progress of the closing and technical traffic opening. According to the investor, the T4 pillar has not been constructed due to the frequent heavy rains. The contractor has deployed measures to stop the flow at least twice, but the upstream water level continues to flow back.

The contractor is currently focusing on completing the beam installation. However, the fact that the T4 pillar cannot be constructed has affected the progress.

In the coming time, the contractor will continue to complete the T4 pillar. Regarding the access road, there is basically enough land to carry out the construction. However, there are still 2 households waiting for resettlement arrangements.
Source: https://vtcnews.vn/cau-thuoc-du-an-280-ty-thi-cong-rua-bo-dan-cho-hoai-chang-thay-thong-xe-ar954529.html