The project has a total investment of more than VND8,925 billion, with an implementation period of 24 months; the 2.2 km long Vung mountain tunnel section passing through Ninh Thuan and Binh Thuan provinces will have an implementation period of 30 months.
In the first days of 2024, the construction site of the Cam Lam - Vinh Hao expressway project is in full swing, ready for the opening day on April 30, connecting the expressway from Ho Chi Minh City to Khanh Hoa province. Among them, the important item is the Vung Mountain tunnel.
Cam Lam - Vinh Hao Expressway project has basically completed all items.
According to Thanh Nien reporters, the main routes have been connected, many items are being urgently constructed, meeting the traffic opening schedule as committed to the Ministry of Transport.
Inside Vung Mountain Tunnel
One of the most important items of the project is the Vung Mountain Tunnel, 2.2km long, consisting of 2 tunnels. Each tunnel has 3 lanes, 14m wide, and will be dug and opened to traffic from August 2023.
Workers are urgently completing the northern tube sections of Vung Tau tunnel.
In the northern tunnel, the excavation work has reached 100%, the concrete lining has reached 95% and the concrete pavement has reached more than 80%. Currently, the construction unit is completing the concrete lining, pavement and installing equipment systems in the tunnel such as ventilation, lighting, fire prevention and fighting systems, etc.
The two ends of the approach road have been paved with asphalt, and the project operator's house at the tunnel entrance towards Binh Thuan has been formed.
Construction and installation of equipment systems in the tunnel such as ventilation, lighting, fire prevention and fighting systems...
Completing the road surface of the northern tunnel

Workers are completing the final stages of the northern tunnel.
In the southern tunnel, due to the weak geological zone, different from the approved technical design documents, the tunnel excavation progress was affected. Currently, the construction unit has overcome the difficulties with technical measures, and at the same time accelerated the construction 3 shifts/day and night to make up for the progress, striving to complete the project on March 30 (1 month ahead of schedule).
Pouring concrete for the southern tunnel
A representative of Project Management Board 85 - Ministry of Transport said that the construction items on the main route are closely following the progress of the bridge and road sections opening at the end of December 2023.
The contractor is also speeding up construction progress and completing the Vung mountain tunnel project.
The contractor is also speeding up construction progress, completing the Vung mountain tunnel project to complete the project on April 30, as committed.