Vietnam.vn - Nền tảng quảng bá Việt Nam

Lighting up 24/7 to construct Vung Mountain tunnel, striving to exceed schedule

Báo Thanh niênBáo Thanh niên29/01/2024


Cam Lam - Vinh Hao Expressway is one of the 3 North - South Expressway projects in phase 1, with a length of 78.5 km, passing through 3 provinces of Khanh Hoa (nearly 5 km), Ninh Thuan (63 km), Binh Thuan (nearly 12 km), invested by the joint venture Deo Ca Group - Company 194.

The project has a total investment of more than VND8,925 billion, with an implementation period of 24 months; the 2.2 km long Vung mountain tunnel section passing through Ninh Thuan and Binh Thuan provinces will have an implementation period of 30 months.

In the first days of 2024, the construction site of the Cam Lam - Vinh Hao expressway project is in full swing, ready for the opening day on April 30, connecting the expressway from Ho Chi Minh City to Khanh Hoa province. Among them, the important item is the Vung Mountain tunnel.

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 1.

Cam Lam - Vinh Hao Expressway project has basically completed all items.

According to Thanh Nien reporters, the main routes have been connected, many items are being urgently constructed, meeting the traffic opening schedule as committed to the Ministry of Transport.

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 2.

Inside Vung Mountain Tunnel

One of the most important items of the project is the Vung Mountain Tunnel, 2.2km long, consisting of 2 tunnels. Each tunnel has 3 lanes, 14m wide, and will be dug and opened to traffic from August 2023.

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 3.

Workers are urgently completing the northern tube sections of Vung Tau tunnel.

In the northern tunnel, the excavation work has reached 100%, the concrete lining has reached 95% and the concrete pavement has reached more than 80%. Currently, the construction unit is completing the concrete lining, pavement and installing equipment systems in the tunnel such as ventilation, lighting, fire prevention and fighting systems, etc.

The two ends of the approach road have been paved with asphalt, and the project operator's house at the tunnel entrance towards Binh Thuan has been formed.

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 4.

Construction and installation of equipment systems in the tunnel such as ventilation, lighting, fire prevention and fighting systems...

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 5.

Completing the road surface of the northern tunnel

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 6.

Workers are completing the final stages of the northern tunnel.

In the southern tunnel, due to the weak geological zone, different from the approved technical design documents, the tunnel excavation progress was affected. Currently, the construction unit has overcome the difficulties with technical measures, and at the same time accelerated the construction 3 shifts/day and night to make up for the progress, striving to complete the project on March 30 (1 month ahead of schedule).

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 7.

Pouring concrete for the southern tunnel

A representative of Project Management Board 85 - Ministry of Transport said that the construction items on the main route are closely following the progress of the bridge and road sections opening at the end of December 2023.

Chong đèn 24/24 thi công hầm núi Vung, phấn đấu vượt tiến độ- Ảnh 8.

The contractor is also speeding up construction progress and completing the Vung mountain tunnel project.

The contractor is also speeding up construction progress, completing the Vung mountain tunnel project to complete the project on April 30, as committed.



Source link

Comment (0)

No data
No data

Same tag

Same category

When community tourism becomes a new rhythm of life on Tam Giang lagoon
Ninh Binh tourist attractions not to be missed
Wandering in the clouds of Dalat
Villages on the Truong Son mountain range

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product