The coastal road project north of An Hai bridge has reached 30% of the contract value.

According to the Provincial Construction Investment Project Management Board, the construction progress of the coastal road project north of An Hai bridge is being accelerated by contractors; the volume of work is nearly 98 billion VND, reaching about 30% of the total contract value, basically in line with the project's construction progress. As for the current construction site, the locality has only handed over 3.4/7.5km, reaching 45%.

Báo Phú YênBáo Phú Yên16/05/2025

Specifically, the section Km3+600-Km4+620 has completed the construction of the foundation, crushed stone aggregate foundation, drainage system, technical sewer, curb, and median strip. The total construction value is 27.5 billion VND, reaching 56% of the contract value. The section Km4+620-Km5+800 has completed the foundation, crushed stone aggregate foundation, drainage system, technical sewer, curb, and median strip. The implementation value is 32 billion VND, reaching 51% of the contract value.

For other sections, units and contractors have also completed part of the roadbed, crushed stone foundation, drainage culverts, technical culverts, and box culverts, with the completed volume from 7-20% of the contract value. In particular, for the section from Km3+600-Km4+800 (the section intersecting with DH31 road), construction units have organized the asphalt concrete paving of about 1.2km to facilitate people's travel.

It is known that the coastal road section north of An Hai bridge is 7.48km long; the starting point intersects with DH31 road (Km3+600), the ending point intersects with the beginning of An Hai bridge (Km11+082). In terms of scale, the section Km3+600-Km6+300 (2.7km long) has a roadbed width of 42m, the section Km6+300-Km11+082 (4.78km long) has a roadbed width of 52m. In addition, the project is also designed with a complete drainage system, technical culverts across the road and a traffic safety system. This project is expected to be completed in May 2026.

Source: https://baophuyen.vn/kinh-te/202505/cong-trinhtuyen-duong-bo-ven-bien-doan-phia-bac-cau-an-hai-dat-30-gia-tri-hop-dong-45e6755/


Comment (0)

No data
No data

Same category

The place where Uncle Ho read the Declaration of Independence
Where President Ho Chi Minh read the Declaration of Independence
Explore the savanna in Nui Chua National Park
Discover Vung Chua - the cloud-covered 'roof' of Quy Nhon beach city

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product