- On the afternoon of October 9, Comrade Doan Thanh Son, Vice Chairman of the Provincial People's Committee chaired a meeting to review the progress of projects under the Pilot Project to build smart border gates.
Attending the meeting were leaders of a number of relevant departments, branches and sectors and leaders of the Party Committee and People's Committee of Hoang Van Thu and Dong Dang communes.
According to the report of the Management Board of Dong Dang - Lang Son Border Gate Economic Zone (KTCK), up to the end of September 2025, at 3 public investment projects under the smart border gate project, there were problems in site clearance, leading to slow construction progress, not meeting requirements.

At the project to invest in the construction of an inter-sectoral office building for functional forces on the dedicated freight transport road at landmark 1088/2-1089, the investor has completed the selection of contractors for 10/11 packages. Regarding site clearance, relevant units have counted 24/24 households, individuals, and residential communities affected by the project. Of which, 5/24 households have received advance payment of more than 326 million VND, handing over an area of 0.21ha...
At the project to expand the dedicated freight road in the area of landmark 1088/2-1089, the Provincial People's Committee has approved the investment policy, feasibility study report and environmental impact assessment report. The functional unit has completed the census of 32/32 households, individuals and organizations; completed the relocation of 9/52 graves...

At the project to expand the specialized freight transport road in the area of landmarks 1119-1120, the construction unit has completed the asphalt concrete pavement to ensure connection with the Chinese side (phase 1); completed the construction investment procedures to implement the expansion of the road from 6 to 14 lanes (phase 2)...
Regarding attracting investment from non-budgetary sources, the Management Board of Dong Dang - Lang Son Economic Zone has completed the selection of investors for the specialized freight transport route in the area of landmark 1088/2-1089.

At the meeting, leaders of departments, branches, sectors, and People's Committees of relevant communes reported on the situation and progress of project implementation according to the fields of the sector and unit . In particular, they pointed out a number of difficulties and problems related to: dumping sites; cemetery land fund for relocating graves; compensation, support, and advance payment plans; land use targets according to planning... At the same time, they proposed a number of solutions to remove difficulties and problems in the process of implementing projects under the project in the coming time.
Speaking at the meeting, the Vice Chairman of the Provincial People's Committee acknowledged the efforts of departments, branches, units, and People's Committees of communes in organizing and implementing tasks related to the project.

Regarding the tasks in the coming time, he requested agencies, units, project investors, and the People's Committees of Dong Dang and Hoang Van Thu communes to continue to focus on reviewing and assigning tasks to closely follow the progress required by the Provincial People's Committee; at the same time, prioritize the arrangement of qualified and experienced human resources to complete the assigned tasks.
Regarding the project of expanding the specialized freight transport road in the area of milestones 1119-1120, phase 1 of the project, the Vice Chairman of the Provincial People's Committee requested the Management Board of Dong Dang - Lang Son Economic Zone to ensure connection conditions and organize traffic; relevant units urgently complete procedures to ensure site clearance before November 10, 2025.
Regarding the project to expand the specialized freight transport road in the area of landmark 1088/2-1089, he requested the Provincial Construction Investment Project Management Board to urgently complete the bidding procedures to sign the contract for the EC package no later than October 17; at the same time, deploy some segments of the package in October if the site conditions are met; Hoang Van Thu Commune People's Committee coordinates with the branch of the Regional Land Fund Development Center to organize inspections and review, determine the location of the land to relocate the graves no later than October 20...
Regarding the project to invest in building an inter-sectoral office for functional forces on the specialized road for transporting goods at landmark 1088/2-1089, he requested the People's Committee of Hoang Van Thu commune to coordinate with relevant units to speed up the progress of site clearance; requested the Department of Agriculture and Environment to coordinate with the People's Committee of the commune to update the rice land index in the planning; the Provincial Construction Investment Project Management Board to complete the design documents and construction drawings...
For non-budget investment projects under the smart border gate project, he assigned the Management Board of Dong Dang - Lang Son Economic Zone to monitor and urge investors to develop implementation plans according to the approved investment policy, focusing on prioritizing the wharf items of the smart border gate.